4840 N TOWNSEND AVE 90041
Certificate Information: 4840 N TOWNSEND AVE 90041
- Application / Permit
- 23014-10000-00200
- Plan Check / Job No.
- B23LA00636
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO SINGLE FAMILY DWELLING TO INCLUDE ENCLOSURE AND CONVERSION OF EXISTING ATTACHED 13'-10" X 12'-3" PATIO COVER TO LIVING AREA - PER ENGINEER
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/18/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 1/19/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 4/10/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 4/13/2023 | DANIEL ABRAMYAN |
| Issued | 4/14/2023 | APPLICANT |
| CofO in Progress | 8/1/2024 | CRAIG VAUGHAN |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
| CofO Issued | 10/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/30/2023 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 3/3/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 3/3/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2023 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Duncan; Lic. No.: NA81058 | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/18/2023 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/19/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/19/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 4/19/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 4/19/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/24/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 5/5/2023 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 5/11/2023 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Wood Construction | 5/11/2023 | Conditional Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/12/2023 | Not Ready for Inspection | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Partial Approval | RUBEN SALAS |
| Insulation | 5/12/2023 | Not Ready for Inspection | RUBEN SALAS |
| Wood Frame | 5/12/2023 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 5/19/2023 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Wood Construction | 5/25/2023 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/5/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/5/2023 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/9/2023 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/9/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/9/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 6/9/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/16/2023 | Corrections Issued | RUBEN SALAS |
| Wood Frame | 6/16/2023 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 6/22/2023 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/22/2023 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/22/2023 | Corrections Issued | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 6/23/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 6/27/2023 | Order to Comply Issued | BRIAN SULLIVAN |
| Special/Order Compliance | 6/29/2023 | Partial Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/4/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/4/2023 | Partial Approval | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 8/4/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 8/4/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/1/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/1/2023 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 9/1/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/1/2023 | Corrections Issued | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 9/13/2023 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/15/2023 | Approved | ROY SPAULDING |
| Insulation | 9/20/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 9/21/2023 | No Access for Inspection | ROY SPAULDING |
| Drywall Nailing | 9/26/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 10/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| Shower Pan | 10/26/2023 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 2/29/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/7/2024 | Approved | CRAIG VAUGHAN |
| Final | 6/7/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 6/7/2024 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 6/7/2024 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 6/7/2024 | Approved | CRAIG VAUGHAN |
| Final | 6/25/2024 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Not Ready | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/18/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 7/18/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 7/18/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 7/18/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Not Ready | CRAIG VAUGHAN |
| ELECTRICAL-Final | 7/30/2024 | Approved | CRAIG VAUGHAN |
| Final | 7/30/2024 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 7/30/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 7/30/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 7/30/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Final | 7/31/2024 | OK to Issue CofO | CRAIG VAUGHAN |
| Gas Test | 7/31/2024 | Approved | CRAIG VAUGHAN |