4840 N TOWNSEND AVE 90041

Certificate Information: 4840 N TOWNSEND AVE 90041

Application / Permit
23014-10000-00200
Plan Check / Job No.
B23LA00636
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO SINGLE FAMILY DWELLING TO INCLUDE ENCLOSURE AND CONVERSION OF EXISTING ATTACHED 13'-10" X 12'-3" PATIO COVER TO LIVING AREA - PER ENGINEER
Permit Issued
Issued on 4/14/2023
Issuing Office
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2023 APPLICANT
Assigned to Plan Check Engineer 1/18/2023 DANIEL ABRAMYAN
Corrections Issued 1/19/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 4/10/2023 DANIEL ABRAMYAN
Plan Check Approved 4/13/2023 DANIEL ABRAMYAN
Issued 4/14/2023 APPLICANT
CofO in Progress 8/1/2024 CRAIG VAUGHAN
Permit Finaled 10/1/2024 RUBEN SALAS
Permit Finaled 10/1/2024 RUBEN SALAS
CofO Issued 10/1/2024 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/30/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 3/3/2023 AMAAN MALIK
Sewer availability Cleared 3/3/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 3/10/2023 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Duncan; Lic. No.: NA81058       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/18/2023 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/19/2023 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 4/19/2023 Not Ready for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 4/19/2023 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 4/19/2023 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/24/2023 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 4/24/2023 Approved CRAIG VAUGHAN
Wood Frame 5/5/2023 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 5/11/2023 Conditional Approval CRAIG VAUGHAN
Deputy Wood Construction 5/11/2023 Conditional Approval CRAIG VAUGHAN
ELECTRICAL-Rough 5/12/2023 Not Ready for Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval RUBEN SALAS
Insulation 5/12/2023 Not Ready for Inspection RUBEN SALAS
Wood Frame 5/12/2023 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 5/19/2023 Corrections Issued BRIAN SULLIVAN
Deputy Wood Construction 5/25/2023 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/26/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 5/26/2023 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 5/26/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 6/5/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 6/5/2023 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 6/9/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 6/9/2023 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 6/9/2023 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 6/9/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 6/16/2023 Corrections Issued RUBEN SALAS
Wood Frame 6/16/2023 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 6/22/2023 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 6/22/2023 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 6/22/2023 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 6/23/2023 Not Ready for Inspection CRAIG VAUGHAN
Special/Order Compliance 6/27/2023 Order to Comply Issued BRIAN SULLIVAN
Special/Order Compliance 6/29/2023 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 8/4/2023 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 8/4/2023 Partial Approval CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 8/4/2023 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 8/4/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 9/1/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 9/1/2023 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 9/1/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 9/1/2023 Corrections Issued CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 9/13/2023 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 9/15/2023 Approved ROY SPAULDING
Insulation 9/20/2023 Approved CRAIG VAUGHAN
Insulation 9/21/2023 No Access for Inspection ROY SPAULDING
Drywall Nailing 9/26/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 10/12/2023 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 10/12/2023 Not Ready for Inspection ROY SPAULDING
Shower Pan 10/26/2023 Approved JOSH MEISTER
ELECTRICAL-Final 2/29/2024 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 6/7/2024 Approved CRAIG VAUGHAN
Final 6/7/2024 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 6/7/2024 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 6/7/2024 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 6/7/2024 Approved CRAIG VAUGHAN
Final 6/25/2024 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Not Ready BRENDAN MORELLI
ELECTRICAL-Final 7/18/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 7/18/2024 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 7/18/2024 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 7/18/2024 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Not Ready CRAIG VAUGHAN
ELECTRICAL-Final 7/30/2024 Approved CRAIG VAUGHAN
Final 7/30/2024 Corrections Issued CRAIG VAUGHAN
Gas Test 7/30/2024 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 7/30/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 7/30/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/30/2024 SGSOV Approved CRAIG VAUGHAN
Final 7/31/2024 OK to Issue CofO CRAIG VAUGHAN
Gas Test 7/31/2024 Approved CRAIG VAUGHAN