7440 W 91ST ST 90045

Certificate Information: 7440 W 91ST ST 90045

Application / Permit
23014-10000-00197
Plan Check / Job No.
B23LA00633
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (27'-0"x21'-10"), 498 SQFT ADDITION W/ROOFTOP DECK ABOVE
Permit Issued
Issued on 4/25/2023
Issuing Office
Current Status
CofO Issued on 8/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 PETER MOSESIAN
Corrections Issued 2/20/2023 PETER MOSESIAN
Quality Review Completed 2/24/2023 OMID HEDAYAT
Plan Check Approved 4/11/2023 PETER MOSESIAN
Issued 4/25/2023 APPLICANT
CofO in Progress 8/10/2024 TEMISTOCLES CAAL
Permit Finaled 8/15/2024 RICHARD STEINBACH
CofO Issued 8/15/2024 RICHARD STEINBACH
Permit Finaled 8/15/2024 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 2/28/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 3/1/2023 JASON NG
Roof/Waste drainage to street Cleared 3/1/2023 JASON NG
Specific Plan Cleared 3/9/2023 JIMMY VIVAR

Contact Information

Contractor Owner-Builder       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/10/2023 Approved BOBBY KEY
Footing/Foundation/Slab 5/10/2023 Approved BOBBY KEY
Underground Mechanical 6/2/2023 Not Ready for Inspection BOBBY KEY
Wood Frame 6/2/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 6/8/2023 Partial Approval BOBBY KEY
Deputy Wood Construction 6/20/2023 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 7/10/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 7/10/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 7/13/2023 No Access for Inspection HERBERT GIRON
ELECTRICAL-Rough 7/21/2023 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Approved BOBBY KEY
HVAC-Rough 7/21/2023 Conditional Approval BOBBY KEY
PLUMBING-Rough 7/21/2023 Approved BOBBY KEY
ELECTRICAL-Rough 7/25/2023 Corrections Issued BOBBY KEY
HVAC-Rough 7/25/2023 Approved BOBBY KEY
ELECTRICAL-Rough 8/18/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 11/6/2023 Approved BOBBY KEY
Green Building Rough 11/6/2023 Approved BOBBY KEY
Insulation 11/6/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 11/6/2023 Partial Approval BOBBY KEY
Insulation 11/8/2023 Approved BOBBY KEY
Drywall Nailing 11/27/2023 Approved BOBBY KEY
Interior/Exterior Lathing 11/27/2023 Corrections Issued BOBBY KEY
Special/Order Compliance 1/29/2024 Partial Inspection BOBBY KEY
ELECTRICAL-Final 5/13/2024 Corrections Issued BOBBY KEY
Shower Pan 5/13/2024 Approved BOBBY KEY
Deck 5/21/2024 Partial Approval BOBBY KEY
Interior/Exterior Lathing 5/21/2024 Approved BOBBY KEY
Interior/Exterior Lathing 5/28/2024 Approved BOBBY KEY
PLUMBING-Final 5/28/2024 Not Ready for Inspection BOBBY KEY
Gas Test 6/7/2024 Approved BOBBY KEY
ELECTRICAL-Final 6/27/2024 Corrections Issued BOBBY KEY
Final 6/27/2024 Corrections Issued BOBBY KEY
Green Building Final 6/27/2024 Corrections Issued BOBBY KEY
HVAC-Final 6/27/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 6/27/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/27/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 6/27/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Final 8/2/2024 Approved BOBBY KEY
Final 8/2/2024 Not Ready for Inspection BOBBY KEY
Green Building Final 8/2/2024 Approved BOBBY KEY
HVAC-Final 8/2/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 8/2/2024 Approved BOBBY KEY
Smoke Detectors 8/2/2024 Approved BOBBY KEY
Final 8/6/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 8/6/2024 Approved BOBBY KEY
Final 8/9/2024 OK to Issue CofO TEMISTOCLES CAAL
Service/Power Release 8/13/2024 Approved BOBBY KEY