122 N WILTON PL 90004

Certificate Information: 122 N WILTON PL 90004

Application / Permit
23014-10000-00196
Plan Check / Job No.
B23LA00632
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) IRREGULARLY SHAPED 20' X 30'8" ADDITION (460 SF) TO REAR OF 1-STORY (E) SFD TO ADD MUDROOM, DEN, AND BATHROOM. WORK TO BE DONE PER WFPP.
Permit Issued
Issued on 8/30/2023
Issuing Office
Current Status
CofO Issued on 3/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2023 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 MADISON ODELL
Corrections Issued 1/27/2023 MADISON ODELL
Applicant returned to address corrections 6/22/2023 PINANK PATEL
Plan Check Approved 7/25/2023 JOE VO
Issued 8/30/2023 APPLICANT
CofO in Progress 12/10/2024 JEFFREY MEAD
CofO in Progress 12/14/2024 JOAQUIN GREENOUGH
CofO in Progress 3/20/2025 JOAQUIN GREENOUGH
Permit Finaled 3/20/2025 DEROLD HAUFF
CofO Issued 3/20/2025 DEROLD HAUFF
Permit Finaled 3/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/1/2023 JESSICA OPINION
Historic monument Cleared 7/18/2023 LAMBERT GIESSINGER
Roof/Waste drainage to street Cleared 7/23/2023 AHMED AMARRAGY

Contact Information

Architect Diradourian,, Richard C; Lic. No.: NA10336       ,
Contractor Remodeling California Inc; Lic. No.: 881905-B       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/15/2023 Approved JEFFREY MEAD
Special/Order Compliance 11/16/2023 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 12/8/2023 Corrections Issued JEFFREY MEAD
Rough-Elec/Plmb/HVAC 12/8/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 12/19/2023 Approved JEFFREY MEAD
Underground Mechanical 12/19/2023 Approved JEFFREY MEAD
ELECTRICAL-Rough 12/29/2023 Not Ready for Inspection JEFFREY MEAD
Interior/Exterior Lathing 12/29/2023 Partial Approval JEFFREY MEAD
ELECTRICAL-Rough 1/4/2024 Approved JEFFREY MEAD
HVAC-Rough 1/4/2024 Approved JEFFREY MEAD
PLUMBING-Rough 1/4/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 1/5/2024 Approved JEFFREY MEAD
Green Building Rough 1/5/2024 Approved JEFFREY MEAD
Insulation 1/8/2024 Approved JEFFREY MEAD
Drywall Nailing 1/18/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 1/18/2024 Approved JEFFREY MEAD
Final 4/12/2024 Corrections Issued JEFFREY MEAD
Green Building Final 4/12/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved JEFFREY MEAD
Smoke Detectors 4/12/2024 Approved JEFFREY MEAD
ELECTRICAL-Final 4/17/2024 Approved ENRIQUE MIRELES
Final 4/17/2024 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 4/17/2024 Approved ENRIQUE MIRELES
Final 12/9/2024 Not Ready for Inspection JEFFREY MEAD
HVAC-Final 12/9/2024 Approved JEFFREY MEAD
Special/Order Compliance 12/17/2024 Corrections Issued JOAQUIN GREENOUGH
Final 3/20/2025 OK to Issue CofO JOAQUIN GREENOUGH