122 N WILTON PL 90004
Certificate Information: 122 N WILTON PL 90004
- Application / Permit
- 23014-10000-00196
- Plan Check / Job No.
- B23LA00632
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) IRREGULARLY SHAPED 20' X 30'8" ADDITION (460 SF) TO REAR OF 1-STORY (E) SFD TO ADD MUDROOM, DEN, AND BATHROOM. WORK TO BE DONE PER WFPP.
- Permit Issued
- Issued on 8/30/2023
- Issuing Office
- Current Status
- CofO Issued on 3/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | MADISON ODELL |
| Corrections Issued | 1/27/2023 | MADISON ODELL |
| Applicant returned to address corrections | 6/22/2023 | PINANK PATEL |
| Plan Check Approved | 7/25/2023 | JOE VO |
| Issued | 8/30/2023 | APPLICANT |
| CofO in Progress | 12/10/2024 | JEFFREY MEAD |
| CofO in Progress | 12/14/2024 | JOAQUIN GREENOUGH |
| CofO in Progress | 3/20/2025 | JOAQUIN GREENOUGH |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
| CofO Issued | 3/20/2025 | DEROLD HAUFF |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | JESSICA OPINION |
| Historic monument | Cleared | 7/18/2023 | LAMBERT GIESSINGER |
| Roof/Waste drainage to street | Cleared | 7/23/2023 | AHMED AMARRAGY |
Contact Information
| Architect | Diradourian,, Richard C; Lic. No.: NA10336 | , |
| Contractor | Remodeling California Inc; Lic. No.: 881905-B | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/15/2023 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 11/16/2023 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/8/2023 | Corrections Issued | JEFFREY MEAD |
| Rough-Elec/Plmb/HVAC | 12/8/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Approved | JEFFREY MEAD |
| Underground Mechanical | 12/19/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 12/29/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Interior/Exterior Lathing | 12/29/2023 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 1/4/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 1/4/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 1/4/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/5/2024 | Approved | JEFFREY MEAD |
| Green Building Rough | 1/5/2024 | Approved | JEFFREY MEAD |
| Insulation | 1/8/2024 | Approved | JEFFREY MEAD |
| Drywall Nailing | 1/18/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 1/18/2024 | Approved | JEFFREY MEAD |
| Final | 4/12/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 4/12/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/12/2024 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 4/12/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 4/17/2024 | Approved | ENRIQUE MIRELES |
| Final | 4/17/2024 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 4/17/2024 | Approved | ENRIQUE MIRELES |
| Final | 12/9/2024 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Final | 12/9/2024 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 12/17/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 3/20/2025 | OK to Issue CofO | JOAQUIN GREENOUGH |