3616 W 59TH ST 90043
Certificate Information: 3616 W 59TH ST 90043
- Application / Permit
- 23014-10000-00182
- Plan Check / Job No.
- B23LA00592
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: PROPOSED 11'-0" x 11'-6" ADDITION TO AND CONVERT (E) DETACHED 18'-8" x 20'-0" GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 8/8/2024
- Issuing Office
- Current Status
- CofO Issued on 9/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2023 | OMAR GARNICA |
| Corrections Issued | 1/24/2023 | OMAR GARNICA |
| Plan Check Approved | 7/29/2024 | SARKIS HARABEDIAN |
| Issued | 8/8/2024 | APPLICANT |
| CofO in Progress | 9/19/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 9/19/2025 | DEROLD HAUFF |
| CofO Issued | 9/19/2025 | DEROLD HAUFF |
| Permit Finaled | 9/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/4/2023 | RIDWAN HARDY |
| Address approval | Cleared | 11/16/2023 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 11/16/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2023 | WALLIE JONG |
| Sewer availability | Cleared | 11/20/2023 | WALLIE JONG |
| Specific Plan | Cleared | 7/17/2024 | ISAIAH ROSS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tamu,, O C; Lic. No.: C29787 | P O BOX 17083 LONG BEACH, CA 90807 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 8/27/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 9/26/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 9/26/2024 | Partial Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/24/2024 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 10/24/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Gas Test | 10/24/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 10/24/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 10/24/2024 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 10/24/2024 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/13/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/13/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 11/13/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| PLUMBING-Rough | 11/13/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/20/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 11/20/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 11/20/2024 | Conditional Approval | AMIR NAZARIAN |
| Rough-Elec/Plmb/HVAC | 11/20/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 12/5/2024 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 12/5/2024 | Partial Approval | LUIS CASTRO |
| Gas Test | 12/5/2024 | Approved | LUIS CASTRO |
| Green Building Rough | 12/5/2024 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 12/5/2024 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 12/5/2024 | Approved | LUIS CASTRO |
| Wood Frame | 12/5/2024 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 12/6/2024 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Conditional Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 12/6/2024 | Partial Approval | LUIS CASTRO |
| Wood Frame | 12/6/2024 | Not Ready for Inspection | LUIS CASTRO |
| Deputy Wood Construction | 12/9/2024 | Conditional Approval | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 12/10/2024 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 12/10/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 12/10/2024 | Approved | JOHN QUINTANILLA |
| Wood Frame | 12/10/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Insulation | 12/13/2024 | Corrections Issued | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 12/18/2024 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 12/18/2024 | Approved | NICHOLAS LOPEZ |
| Insulation | 12/18/2024 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 1/3/2025 | Corrections Issued | AMIR NAZARIAN |
| Drywall Nailing | 1/13/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 4/7/2025 | Partial Approval | WAYNE REGESTER |
| Final | 4/7/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 4/7/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 4/7/2025 | Partial Approval | WAYNE REGESTER |
| PLUMBING-Final | 4/7/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Service/Power Release | 4/7/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 4/7/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 4/11/2025 | Approved | WAYNE REGESTER |
| Final | 7/29/2025 | Corrections Issued | WAYNE REGESTER |
| Green Building Final | 7/29/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Approved | WAYNE REGESTER |
| Final | 8/15/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 8/28/2025 | Corrections Issued | MICHAEL LEWIS |
| Final | 9/19/2025 | OK to Issue CofO | SALVADOR MARTINEZ |