2021 S BUTLER AVE 90025

Certificate Information: 2021 S BUTLER AVE 90025

Application / Permit
23014-10000-00166
Plan Check / Job No.
B23LA00534
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND 34'-10.5" X 34'-1.75" IRREGULAR SHAPED ADDITION TO SINGLE FAMILY DWELLING - WORK PER ENGINEERING.
Permit Issued
Issued on 3/20/2023
Issuing Office
Current Status
CofO Issued on 6/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2023 APPLICANT
Assigned to Plan Check Engineer 2/3/2023 ISIS ARGUETA
Corrections Issued 2/4/2023 ISIS ARGUETA
Applicant returned to address corrections 3/10/2023 ISIS ARGUETA
Plan Check Approved 3/19/2023 DANIEL ABRAMYAN
Issued 3/20/2023 APPLICANT
CofO in Progress 6/9/2025 MICHAEL PELHAM
Permit Finaled 6/10/2025 RICHARD STEINBACH
CofO Issued 6/10/2025 RICHARD STEINBACH
Permit Finaled 6/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/15/2023 JASON NG
Sewer availability Cleared 2/15/2023 JASON NG
Specific Plan Cleared 2/15/2023 KYLE WINSTON
Roof/Waste drainage to street Cleared 3/9/2023 JASON NG

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/31/2023 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 5/31/2023 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Partial Approval JESUS PINEDA
Insulation 6/27/2023 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 8/10/2023 Not Ready for Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Corrections Issued MICHAEL PELHAM
Green Building Rough 8/10/2023 Not Ready for Inspection MICHAEL PELHAM
Deputy Wood Construction 8/16/2023 Conditional Approval DAVID FEILER
HVAC-Rough 8/21/2023 No Access for Inspection ARAM AVEDISIAN
PLUMBING-Rough 8/21/2023 No Access for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 8/23/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 8/23/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 8/23/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 8/30/2023 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Approval DAVID FEILER
Insulation 9/14/2023 Approved BEN MOLSTAD
BUILDING-Rough-Frame 9/21/2023 Corrections Issued ARAM AVEDISIAN
Green Building Rough 9/21/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/2/2023 Partial Approval BEN MOLSTAD
HVAC-Rough 10/2/2023 Approved BEN MOLSTAD
Interior/Exterior Lathing 10/2/2023 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 10/23/2023 Partial Approval BEN MOLSTAD
Interior/Exterior Lathing 10/23/2023 Partial Approval BEN MOLSTAD
Shower Pan 10/23/2023 Approved BEN MOLSTAD
Drywall Nailing 11/27/2023 Approved BEN MOLSTAD
BUILDING-Rough-Frame 3/19/2024 Approved CARLOS MATAMOROS
Final 3/19/2024 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 3/19/2024 Approved CARLOS MATAMOROS
Green Building Final 3/19/2024 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 3/19/2024 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 6/9/2025 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 6/9/2025 Conditional Approval MICHAEL PELHAM
Final 6/9/2025 OK to Issue CofO MICHAEL PELHAM