2021 S BUTLER AVE 90025
Certificate Information: 2021 S BUTLER AVE 90025
- Application / Permit
- 23014-10000-00166
- Plan Check / Job No.
- B23LA00534
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND 34'-10.5" X 34'-1.75" IRREGULAR SHAPED ADDITION TO SINGLE FAMILY DWELLING - WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2023 | ISIS ARGUETA |
| Corrections Issued | 2/4/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 3/10/2023 | ISIS ARGUETA |
| Plan Check Approved | 3/19/2023 | DANIEL ABRAMYAN |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 6/9/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
| CofO Issued | 6/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2023 | JASON NG |
| Sewer availability | Cleared | 2/15/2023 | JASON NG |
| Specific Plan | Cleared | 2/15/2023 | KYLE WINSTON |
| Roof/Waste drainage to street | Cleared | 3/9/2023 | JASON NG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/31/2023 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 5/31/2023 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Partial Approval | JESUS PINEDA |
| Insulation | 6/27/2023 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/10/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Corrections Issued | MICHAEL PELHAM |
| Green Building Rough | 8/10/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| Deputy Wood Construction | 8/16/2023 | Conditional Approval | DAVID FEILER |
| HVAC-Rough | 8/21/2023 | No Access for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/21/2023 | No Access for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 8/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/23/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/30/2023 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Corrections Issued | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Partial Approval | DAVID FEILER |
| Insulation | 9/14/2023 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 9/21/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Rough | 9/21/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/2/2023 | Partial Approval | BEN MOLSTAD |
| HVAC-Rough | 10/2/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/2/2023 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/23/2023 | Partial Approval | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/23/2023 | Partial Approval | BEN MOLSTAD |
| Shower Pan | 10/23/2023 | Approved | BEN MOLSTAD |
| Drywall Nailing | 11/27/2023 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 3/19/2024 | Approved | CARLOS MATAMOROS |
| Final | 3/19/2024 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/19/2024 | Approved | CARLOS MATAMOROS |
| Green Building Final | 3/19/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/19/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 3/19/2024 | Approved | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 6/9/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 6/9/2025 | Conditional Approval | MICHAEL PELHAM |
| Final | 6/9/2025 | OK to Issue CofO | MICHAEL PELHAM |