7310-7312 N CALDUS AVE 91406

Certificate Information: 7310-7312 N CALDUS AVE 91406

Application / Permit
23014-10000-00155
Plan Check / Job No.
B23LA00491
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
addition and convert attached garage into ADU in existing one story single family dewlling per WFPP. (Attached ADU per Ordinance, LAMC 12.22 A.33(c) and (e))
Permit Issued
Issued on 3/10/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2023 APPLICANT
Assigned to Plan Check Engineer 1/15/2023 AUNG SOE
Corrections Issued 1/18/2023 AUNG SOE
Building Plans Picked Up 1/24/2023 APPLICANT
Applicant returned to address corrections 3/8/2023 VICTOR CHEN
Plan Check Approved 3/10/2023 JOSEPH RAFOLS
Issued 3/10/2023 APPLICANT
CofO in Progress 8/28/2023 RAUL OLAGI
Permit Finaled 9/27/2023 RUBEN SALAS
CofO Issued 9/27/2023 RUBEN SALAS
Permit Finaled 9/27/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/27/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 2/27/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 2/28/2023 ROMAN GUTIERREZ
Sewer availability Cleared 2/28/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/15/2023 Approved RAUL OLAGI
PLUMBING-Rough 4/3/2023 Partial Approval RAUL OLAGI
Sewer 4/3/2023 Approved RAUL OLAGI
Deputy Drilled-In Anchors 4/12/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 4/14/2023 Approved RAUL OLAGI
Wood Frame 5/19/2023 No Access for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Approved RAUL OLAGI
Deputy Drilled-In Anchors 5/24/2023 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 6/9/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 6/9/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 6/9/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 6/14/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 6/14/2023 Approved RAUL OLAGI
Green Building Rough 6/14/2023 Approved RAUL OLAGI
HVAC-Rough 6/14/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 6/14/2023 Approved RAUL OLAGI
HVAC-Rough 6/28/2023 Approved RAUL OLAGI
Insulation 6/28/2023 Approved RAUL OLAGI
Drywall Nailing 7/5/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 7/27/2023 Approved RAUL OLAGI
Shower Pan 7/27/2023 Approved RAUL OLAGI
Final 8/23/2023 Corrections Issued RAUL OLAGI
Green Building Final 8/23/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 8/23/2023 Approved RAUL OLAGI
Final 8/28/2023 OK to Issue CofO RAUL OLAGI