4192 S HARVARD BLVD 90062
Certificate Information: 4192 S HARVARD BLVD 90062
- Application / Permit
- 23014-10000-00083
- Plan Check / Job No.
- B23LA00162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: REMOVE ENTIRE (E) GARAGE EXCEPT ONE WALL AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT WITH 25'-0" x 22'-3"ADDITION TO COMPLY WITH LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Current Status
- CofO Issued on 11/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | GURUNATH NESARAJAH |
| Corrections Issued | 1/17/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 3/19/2023 | GURUNATH NESARAJAH |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 11/7/2023 | SABAS ALONSO |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
| CofO Issued | 11/26/2023 | DEROLD HAUFF |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2023 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 2/27/2023 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 3/9/2023 | CELINA MORENO |
| Sewer availability | Cleared | 3/9/2023 | CELINA MORENO |
Contact Information
| Contractor | Greentech Builders Inc; Lic. No.: 999332-B | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/2/2023 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 5/2/2023 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/8/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 5/8/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 5/8/2023 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/1/2023 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 6/9/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 6/9/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/9/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 6/9/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 6/13/2023 | Approved | SABAS ALONSO |
| Gas Test | 6/13/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 6/13/2023 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 6/13/2023 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/15/2023 | Approved | SABAS ALONSO |
| Gas Test | 6/15/2023 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 6/15/2023 | Approved | SABAS ALONSO |
| Insulation | 6/26/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 7/3/2023 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 7/14/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/19/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 7/26/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/31/2023 | Approved | CHARLES BOGHOSKHAN |
| Gas Test | 8/21/2023 | Corrections Issued | SABAS ALONSO |
| Gas Test | 8/23/2023 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Final | 8/28/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 8/28/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 8/28/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/30/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 8/30/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 9/5/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 9/7/2023 | Approved | STUART CHAPMAN |
| Final | 9/7/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 9/7/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 9/7/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 9/7/2023 | Approved | STUART CHAPMAN |
| Pre-Inspection | 9/29/2023 | Corrections Issued | SABAS ALONSO |
| Final | 11/6/2023 | OK to Issue CofO | SABAS ALONSO |