13674 W BAYLISS ROAD 90049
Certificate Information: 13674 W BAYLISS ROAD 90049
- Application / Permit
- 23014-10000-00069
- Plan Check / Job No.
- B22LA26806
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan ADDITION TO EXISTING SINGLE FAMILY DWELLING; CONVERT EXISTING CARPORT TO GARAGE AND ADD 271 SQ FT; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/17/2023
- Issuing Office
- Current Status
- CofO Issued on 10/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | SELLA BENYAMIN |
| Corrections Issued | 1/31/2023 | SELLA BENYAMIN |
| Quality Review Completed | 2/2/2023 | STEVEN KIM |
| Applicant returned to address corrections | 8/18/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 9/12/2023 | SELLA BENYAMIN |
| Plan Check Approved | 9/15/2023 | SELLA BENYAMIN |
| Plan Check Approved | 10/12/2023 | SELLA BENYAMIN |
| Issued | 10/17/2023 | APPLICANT |
| CofO in Progress | 10/24/2025 | KEVIN SARGSYAN |
| Permit Finaled | 10/29/2025 | RICHARD STEINBACH |
| CofO Issued | 10/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/8/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 5/8/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 5/8/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 5/8/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2023 | JASON NG |
| Sewer availability | Cleared | 5/10/2023 | JASON NG |
| Low Impact Development | Cleared | 8/9/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 8/9/2023 | ANTHONY MAINEZ |
| Public Works-Highway Ded. | Cleared | 8/13/2025 | CHRISTINE REUSCH |
| Public Works-Open Permits | Cleared | 8/13/2025 | CHRISTINE REUSCH |
| Public Works-Sewers | Cleared | 8/13/2025 | CHRISTINE REUSCH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/23/2023 | Partial Inspection | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 12/6/2023 | Partial Inspection | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 5/30/2024 | Corrections Issued | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 6/1/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/17/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/19/2024 | Corrections Issued | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 7/19/2024 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/23/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/9/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/12/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 11/13/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 11/15/2024 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/15/2024 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/20/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/20/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/22/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/22/2024 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 11/22/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 11/22/2024 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/2/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 12/4/2024 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/5/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 12/5/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/17/2024 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 12/17/2024 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/24/2024 | Approved | KEVIN SARGSYAN |
| Shower Pan | 1/31/2025 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | KEVIN SARGSYAN |
| Shower Pan | 2/6/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/11/2025 | Approved | KEVIN SARGSYAN |
| Sewer | 4/15/2025 | Approved | KEVIN SARGSYAN |
| Gas Test | 4/30/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/30/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/1/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/6/2025 | Corrections Issued | KEVIN SARGSYAN |
| Sewer | 5/7/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/13/2025 | Corrections Issued | KEVIN SARGSYAN |
| Smoke Detectors | 6/13/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 6/16/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 6/16/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/17/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 6/17/2025 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 6/17/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 6/24/2025 | Approved | KEVIN SARGSYAN |
| Final | 10/24/2025 | OK to Issue CofO | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 10/24/2025 | Approved | KEVIN SARGSYAN |
| Green Building Final | 10/24/2025 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/24/2025 | SGSOV Approved | KEVIN SARGSYAN |