5129 N WINDERMERE AVE 90041

Certificate Information: 5129 N WINDERMERE AVE 90041

Application / Permit
23014-10000-00055
Plan Check / Job No.
B22LA26778
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan ADDITION AND PARTIAL REMODEL TO EXISTING SINGLE FAMILY RESIDENCE. TOTAL ADDITION SIZE: 298 SF. PER ENGINEERING DESIGN. **PC to generate Alter/Repair app for garage
Permit Issued
Issued on 7/26/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2023 ALFREDO JARA
Corrections Issued 1/12/2023 ALFREDO JARA
Applicant returned to address corrections 2/20/2023 HANS SANTIAGO
Plan Check Approved 2/23/2023 ANDREW SANTIAGO
Issued 7/26/2023 APPLICANT
CofO in Progress 3/27/2024 CRAIG VAUGHAN
Permit Finaled 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/2/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 2/10/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/14/2023 CELINA MORENO

Contact Information

Architect Cooke,, Barrett H; Lic. No.: NA37365       ,
Contractor Jas General Construction; Lic. No.: 1026356-B       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/2/2023 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/3/2023 Approved CRAIG VAUGHAN
Deputy Wood Construction 11/17/2023 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 11/30/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 11/30/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 11/30/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 11/30/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/4/2023 Partial Approval CRAIG VAUGHAN
Insulation 12/5/2023 Approved ROY SPAULDING
Drywall Nailing 12/8/2023 Approved CRAIG VAUGHAN
Shower Pan 12/8/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/11/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 3/21/2024 Approved CRAIG VAUGHAN
Final 3/21/2024 OK to Issue CofO CRAIG VAUGHAN
Green Building Final 3/21/2024 Approved CRAIG VAUGHAN
Green Building Rough 3/21/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/21/2024 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 3/21/2024 Approved CRAIG VAUGHAN