2713 S CEILHUNT AVE 90064
Certificate Information: 2713 S CEILHUNT AVE 90064
- Application / Permit
- 23014-10000-00044
- Plan Check / Job No.
- B22LA26768
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 18'-6" X 19'-2" ADDITION AND REMODEL TO EXISTING SINGLE-FAMILY DWELLING
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Current Status
- CofO Issued on 3/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 1/11/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 3/2/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 6/26/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 7/15/2023 | MOHAMMAD ESMAILI |
| No Progress | 3/12/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/12/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/12/2024 | ALEC MOUSAKHANIAN |
| Issued | 6/17/2024 | APPLICANT |
| CofO in Progress | 2/27/2026 | EVAN COOPER |
| Permit Finaled | 3/2/2026 | RICHARD STEINBACH |
| CofO Issued | 3/2/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/2/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/27/2023 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2023 | JENSON LEE |
| Low Impact Development | Cleared | 6/23/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/23/2023 | DARIN LAM |
| Public Works-Highway Ded. | Cleared | 10/22/2025 | CHRISTINE REUSCH |
| Public Works-Open Permits | Cleared | 10/22/2025 | CHRISTINE REUSCH |
| Public Works-Sewers | Cleared | 10/22/2025 | CHRISTINE REUSCH |
Contact Information
| Contractor | Kofler Consulting Inc; Lic. No.: 1022557-B | , |
| Contractor | Kofler Design Build; Lic. No.: 1022557-B | , |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/21/2024 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 6/25/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 7/1/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Partial Approval | JESUS PINEDA |
| Insulation | 7/10/2024 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 7/15/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 10/23/2024 | Approved | DANIEL VERA |
| HVAC-Rough | 10/23/2024 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 10/23/2024 | Approved | DANIEL VERA |
| Wood Frame | 10/23/2024 | No Access for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Approved | DANIEL VERA |
| HVAC-Rough | 10/25/2024 | Corrections Issued | DANIEL VERA |
| Wood Frame | 10/25/2024 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 11/8/2024 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | KIRK SANDERS |
| Green Building Rough | 11/13/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 11/13/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 11/13/2024 | Partial Approval | KIRK SANDERS |
| Insulation | 11/19/2024 | Not Ready for Inspection | DANIEL VERA |
| Insulation | 11/20/2024 | Not Ready for Inspection | DANIEL VERA |
| Insulation | 11/25/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 12/6/2024 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 1/6/2025 | Approved | DANIEL VERA |
| Shower Pan | 1/6/2025 | Approved | DANIEL VERA |
| Final | 5/7/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 5/7/2025 | Not Ready for Inspection | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 5/7/2025 | SGSOV Not Ready | WILBER ROSALES |
| Smoke Detectors | 5/7/2025 | Not Ready for Inspection | WILBER ROSALES |
| Final | 2/24/2026 | Corrections Issued | ARAM AVEDISIAN |
| Final | 2/24/2026 | No Access for Inspection | ARAM AVEDISIAN |
| Green Building Final | 2/24/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 2/24/2026 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/27/2026 | Approved | EVAN COOPER |
| Final | 2/27/2026 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 2/27/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 2/27/2026 | Approved | EVAN COOPER |