1755 N OLD RANCH ROAD 90049
Certificate Information: 1755 N OLD RANCH ROAD 90049
- Application / Permit
- 23014-10000-00005
- Plan Check / Job No.
- B22LA26728
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **EPLAN** Addition, and Remodel to (E) SFD . Remove and Reframe portion of building including new roof, new skylights, and vaulted ceiling . **see comments; add DWP note to the plans**
- Permit Issued
- Issued on 4/10/2023
- Issuing Office
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2023 | GEORGE ALVAREZ |
| Corrections Issued | 1/10/2023 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 3/21/2023 | GEORGE ALVAREZ |
| Plan Check Approved | 4/7/2023 | SAMUEL GONZALEZ |
| Issued | 4/10/2023 | APPLICANT |
| CofO in Progress | 11/6/2025 | KEVIN SARGSYAN |
| Permit Finaled | 11/21/2025 | RICHARD STEINBACH |
| CofO Issued | 11/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/10/2023 | GEORGE ALVAREZ |
| BHO/Hillside ordinance | Cleared | 1/19/2023 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 1/19/2023 | CATHERINE ADROVER |
| BHO/Hillside ordinance | Cleared | 1/19/2023 | CATHERINE ADROVER |
| Miscellaneous | Cleared | 1/20/2023 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2023 | AHMED AMARRAGY |
| Roof/Waste drainage to street | Cleared | 2/21/2023 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 3/7/2023 | AHMED AMARRAGY |
| Construction near power lines | Cleared | 3/15/2023 | NADER ISKANDER |
| Miscellaneous | Cleared | 3/21/2023 | GEORGE ALVAREZ |
| Miscellaneous | Cleared | 3/26/2023 | GEORGE ALVAREZ |
Contact Information
| Architect | Musolino,, John Michael; Lic. No.: C33574 | 4928 ASTERIA ST TORRANCE, CA 90503 |
| Contractor | Mc&Y Construction Inc; Lic. No.: 910993-B | , |
| Contractor | Servistar Construction; Lic. No.: 910993-B | , |
| Engineer | Trevellin,, Maurizio; Lic. No.: NA71368 | , |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/10/2023 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/25/2023 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 7/19/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/6/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/2/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/2/2023 | Corrections Issued | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 11/2/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 11/2/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/2/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/2/2023 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/9/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/9/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 11/30/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/30/2023 | Approved | KEVIN SARGSYAN |
| Shower Pan | 11/30/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/19/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 8/5/2025 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/5/2025 | No Access for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 8/5/2025 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 8/5/2025 | No Access for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/5/2025 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 8/5/2025 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 11/6/2025 | Approved | KEVIN SARGSYAN |
| Final | 11/6/2025 | OK to Issue CofO | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/6/2025 | Approved | KEVIN SARGSYAN |
| Green Building Final | 11/6/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 11/6/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 11/6/2025 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 11/6/2025 | Approved | KEVIN SARGSYAN |