3911 S FLOWER DR 1-4 90037
Certificate Information: 3911 S FLOWER DR 1-4 90037
- Application / Permit
- 23012-20000-00008
- Plan Check / Job No.
- B23VN14393
- Group
- Building
- Type
- Bldg-Relocation
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- RELOCATION OF (E) 2-STORY 4-UNIT APT BUILDING FROM 3941 S FLOWER DR TO 3911 S FLOWER DR
- Permit Issued
- Issued on 4/19/2024
- Issuing Office
- Current Status
- Issued on 4/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/19/2023 | APPLICANT |
| Assigned to Zoning Architect | 10/26/2023 | SARHAD GHEVANDIAN |
| Assigned to Plan Check Engineer | 11/2/2023 | MANUEL MONTUFAR |
| Corrections Issued | 11/20/2023 | MANUEL MONTUFAR |
| Quality Review Completed | 11/21/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 1/17/2024 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 3/5/2024 | MANUEL MONTUFAR |
| Plan Check Approved | 4/19/2024 | MANUEL MONTUFAR |
| Issued | 4/19/2024 | APPLICANT |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 12/8/2023 | LAMBERT GIESSINGER |
| Historic Resource Verification | Cleared | 12/8/2023 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 12/8/2023 | LAMBERT GIESSINGER |
| Hydrant and Access approval | Cleared | 12/8/2023 | KURT CORRAL |
| "D" conditions | Cleared | 12/18/2023 | ERIN STRELICH |
| "Q" conditions | Cleared | 12/18/2023 | ERIN STRELICH |
| "T" removal | Cleared | 12/18/2023 | ERIN STRELICH |
| CPC | Cleared | 12/18/2023 | ERIN STRELICH |
| Frnt yard landscape/Water mgmt | Cleared | 12/18/2023 | ERIN STRELICH |
| Miscellaneous | Cleared | 12/18/2023 | ERIN STRELICH |
| Miscellaneous | Cleared | 12/18/2023 | ERIN STRELICH |
| Miscellaneous | Cleared | 12/18/2023 | ERIN STRELICH |
| Miscellaneous | Cleared | 12/18/2023 | ERIN STRELICH |
| Miscellaneous | Cleared | 12/18/2023 | ERIN STRELICH |
| ZA Case | Cleared | 12/18/2023 | ERIN STRELICH |
| ZI | Cleared | 12/18/2023 | ERIN STRELICH |
| Address approval | Cleared | 12/19/2023 | TREVOR QUAN |
| Permit | Cleared | 12/19/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 12/19/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2023 | TREVOR QUAN |
| Redevelopment Project Area | Cleared | 1/31/2024 | ELIZABETH GALLARDO |
| SB8 RUD | Cleared | 1/31/2024 | JASON WELLS |
| Tenant Habitability Plan | Cleared | 1/31/2024 | JASON WELLS |
| Low Impact Development (LID) | Cleared | 2/3/2024 | MARTIN FRAGOSO |
| Bicycle Parking | Cleared | 2/8/2024 | KATHERINE MENDOZA |
| Roof/Waste drainage to street | Cleared | 2/22/2024 | ARMEN MEHRABIAN |
| Miscellaneous | Cleared | 4/18/2024 | ERIN STRELICH |
| Zoning Plan Check | Cleared | 4/18/2024 | Joe Vo |
Contact Information
| Architect | Lesak,, John D; Lic. No.: C26607 | 1242 KOLLE AVENUE SOUTH PASADENA, CA 91030 |
| Contractor | L M K Ca Construction Llc; Lic. No.: 1112639-B | 315 OCONEE STREET ATHENS, GA 30601 |
| Engineer | Mahjoub,, Nina; Lic. No.: C78947 | 523 WEST 6TH STREET SUITE 1122 LOS ANGELES, CA 90014 |
| Engineer | Powers,, Brian Frederick; Lic. No.: C75902 | 5712 S. VICTORIA AVE LOS ANGELES, CA 90043 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/30/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 5/1/2024 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 5/20/2024 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 9/20/2024 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 9/27/2024 | Partial Approval | JAMES POWERS |