Application / Permit
23012-20000-00008
Plan Check / Job No.
B23VN14393
Group
Building
Type
Bldg-Relocation
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
RELOCATION OF (E) 2-STORY 4-UNIT APT BUILDING FROM 3941 S FLOWER DR TO 3911 S FLOWER DR
Permit Issued
Issued on 4/19/2024
Issuing Office
Current Status
Issued on 4/19/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/19/2023 APPLICANT
Assigned to Zoning Architect 10/26/2023 SARHAD GHEVANDIAN
Assigned to Plan Check Engineer 11/2/2023 MANUEL MONTUFAR
Corrections Issued 11/20/2023 MANUEL MONTUFAR
Quality Review Completed 11/21/2023 EUGENE BARBEAU
Applicant returned to address corrections 1/17/2024 MANUEL MONTUFAR
Applicant returned to address corrections 3/5/2024 MANUEL MONTUFAR
Plan Check Approved 4/19/2024 MANUEL MONTUFAR
Issued 4/19/2024 APPLICANT

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 12/8/2023 LAMBERT GIESSINGER
Historic Resource Verification Cleared 12/8/2023 LAMBERT GIESSINGER
Historic monument Cleared 12/8/2023 LAMBERT GIESSINGER
Hydrant and Access approval Cleared 12/8/2023 KURT CORRAL
"D" conditions Cleared 12/18/2023 ERIN STRELICH
"Q" conditions Cleared 12/18/2023 ERIN STRELICH
"T" removal Cleared 12/18/2023 ERIN STRELICH
CPC Cleared 12/18/2023 ERIN STRELICH
Frnt yard landscape/Water mgmt Cleared 12/18/2023 ERIN STRELICH
Miscellaneous Cleared 12/18/2023 ERIN STRELICH
Miscellaneous Cleared 12/18/2023 ERIN STRELICH
Miscellaneous Cleared 12/18/2023 ERIN STRELICH
Miscellaneous Cleared 12/18/2023 ERIN STRELICH
Miscellaneous Cleared 12/18/2023 ERIN STRELICH
ZA Case Cleared 12/18/2023 ERIN STRELICH
ZI Cleared 12/18/2023 ERIN STRELICH
Address approval Cleared 12/19/2023 TREVOR QUAN
Permit Cleared 12/19/2023 TREVOR QUAN
Sewer availability Cleared 12/19/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/20/2023 TREVOR QUAN
Redevelopment Project Area Cleared 1/31/2024 ELIZABETH GALLARDO
SB8 RUD Cleared 1/31/2024 JASON WELLS
Tenant Habitability Plan Cleared 1/31/2024 JASON WELLS
Low Impact Development (LID) Cleared 2/3/2024 MARTIN FRAGOSO
Bicycle Parking Cleared 2/8/2024 KATHERINE MENDOZA
Roof/Waste drainage to street Cleared 2/22/2024 ARMEN MEHRABIAN
Miscellaneous Cleared 4/18/2024 ERIN STRELICH
Zoning Plan Check Cleared 4/18/2024 Joe Vo

Contact Information

Architect Lesak,, John D; Lic. No.: C26607 1242 KOLLE AVENUE      SOUTH PASADENA, CA 91030
Contractor L M K Ca Construction Llc; Lic. No.: 1112639-B 315 OCONEE STREET      ATHENS, GA 30601
Engineer Mahjoub,, Nina; Lic. No.: C78947 523 WEST 6TH STREET SUITE 1122      LOS ANGELES, CA 90014
Engineer Powers,, Brian Frederick; Lic. No.: C75902 5712 S. VICTORIA AVE      LOS ANGELES, CA 90043

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/30/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/1/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/20/2024 Approved RAFAEL ESPINOZA
Wood Frame 9/20/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 9/27/2024 Partial Approval JAMES POWERS