3977 S FLOWER DR #1-4 90037
Certificate Information: 3977 S FLOWER DR #1-4 90037
- Application / Permit
- 23012-20000-00006
- Plan Check / Job No.
- B23VN12262
- Group
- Building
- Type
- Bldg-Relocation
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- RELOCATION OF (E) 2-STORY 4-UNIT APT BUILDING FROM 3931 S. FLOWER DR TO 3977 S. FLOWER DRIVE _BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13. (ANY ADDITION AND ALTERATION TO BE UNDER SEPARATE PLAN CHECK AND PERMIT).
- Permit Issued
- Issued on 4/4/2024
- Issuing Office
- Current Status
- Issued on 4/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | DAWN MC NULTY |
| Corrections Issued | 10/16/2023 | DAWN MC NULTY |
| Quality Review Completed | 10/16/2023 | STEVEN KIM |
| Applicant returned to address corrections | 12/7/2023 | DAWN MC NULTY |
| Applicant returned to address corrections | 1/12/2024 | DAWN MC NULTY |
| Applicant returned to address corrections | 1/24/2024 | DAWN MC NULTY |
| Applicant returned to address corrections | 2/8/2024 | DAWN MC NULTY |
| Applicant returned to address corrections | 2/22/2024 | DAWN MC NULTY |
| Applicant returned to address corrections | 3/18/2024 | DAWN MC NULTY |
| Plan Check Approved | 4/3/2024 | DAWN MC NULTY |
| Plan Check Approved | 4/4/2024 | DAWN MC NULTY |
| Issued | 4/4/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2023 | TREVOR QUAN |
| Certificate of Compliance | Cleared | 10/31/2023 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 11/3/2023 | TREVOR QUAN |
| Frnt yard landscape/Water mgmt | Cleared | 11/20/2023 | JASON CHAN |
| ZI | Cleared | 11/20/2023 | JASON CHAN |
| DAS Clearance | Cleared | 11/28/2023 | DAWN MC NULTY |
| ZI | Cleared | 11/28/2023 | JASON CHAN |
| Green Code | Cleared | 11/30/2023 | AARON COSTA |
| Miscellaneous | Cleared | 11/30/2023 | ERIN STRELICH |
| Bicycle Parking | Cleared | 1/4/2024 | KATHERINE MENDOZA |
| Miscellaneous | Cleared | 1/30/2024 | DAWN MC NULTY |
| SB8 RUD | Cleared | 1/31/2024 | JASON WELLS |
| ZI | Cleared | 1/31/2024 | ELIZABETH GALLARDO |
| Low Impact Development (LID) | Cleared | 2/3/2024 | MARTIN FRAGOSO |
| Permit | Cleared | 2/22/2024 | ARMEN MEHRABIAN |
| Roof/Waste drainage to street | Cleared | 2/22/2024 | ARMEN MEHRABIAN |
| Hydrant and Access approval | Cleared | 3/26/2024 | KURT CORRAL |
Contact Information
| Architect | Lesak,, John D; Lic. No.: C26607 | 1242 KOLLE AVENUE SOUTH PASADENA, CA 91030 |
| Contractor | L M K Ca Construction Llc; Lic. No.: 1112639-B | 315 OCONEE STREET ATHENS, GA 30601 |
| Engineer | Kim,, Carl C; Lic. No.: GE2620 | 945 BAILEYANA ROAD HILLSBOROUGH, CA 94010 |
| Engineer | Mahjoub,, Nina; Lic. No.: C78947 | 21400 BURBANK BLVD 114 WOODLAND HILLS, CA 91367 |
| Engineer | Powers,, Brian Frederick; Lic. No.: C75902 | 5712 S. VICTORIA AVE LOS ANGELES, CA 90043 |
| Landscape Architect | Carroll,, Stephen J.; Lic. No.: LA3977 | 529 BAUGHMAN AVE CLAREMONT, CA 91711 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/25/2024 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 5/16/2024 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 5/20/2024 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/28/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 7/24/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 7/31/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/2/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/6/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/8/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/12/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/10/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/12/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/13/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/19/2024 | Partial Approval | JAMES POWERS |
| Wood Frame | 9/20/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 9/23/2024 | Partial Approval | JAMES POWERS |
| Wood Frame | 9/27/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/23/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/25/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 11/8/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 12/10/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/16/2025 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/31/2025 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 2/18/2025 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/3/2025 | Partial Approval | JAMES POWERS |