837 1/2 N NEPTUNE AVE 90744

Certificate Information: 837 1/2 N NEPTUNE AVE 90744

Application / Permit
23010-40000-01559
Plan Check / Job No.
B23SP00060
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY ACCESSORY DWELLING UNIT (ADU) PER GCS 65852.2(e)(1)(B) AT REAR OF LOT.
Permit Issued
Issued on 5/30/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 6/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2023 APPLICANT
Assigned to Plan Check Engineer 4/17/2023 LAWRENCE QUIRANTE
Corrections Issued 4/18/2023 LAWRENCE QUIRANTE
Plan Check Approved 5/25/2023 SERGIO SILVA
Issued 5/30/2023 APPLICANT
CofO in Progress 5/1/2025 EUGENE CASSIDY
CofO Issued 6/18/2025 ANSON MAGLASANG
Permit Finaled 6/18/2025 ANSON MAGLASANG

Permit Application Clearance Information

"Q" conditions Cleared 4/19/2023 DANIEL CORONADO
Address approval Cleared 4/25/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 4/27/2023 ANA SORIANO
Sewer availability Cleared 4/27/2023 ANA SORIANO
Low Impact Development (LID) Cleared 5/17/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/18/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/2/2023 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 8/8/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval JOHN KLARIN
PLUMBING-Rough 11/29/2023 Partial Approval JOHN KLARIN
Insulation 12/7/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 2/16/2024 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval EUGENE CASSIDY
Green Building Rough 2/16/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 2/16/2024 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 2/16/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/12/2024 Corrections Issued EUGENE CASSIDY
Green Building Rough 3/12/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/23/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 4/23/2024 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 4/23/2024 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 5/2/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/2/2024 Approved EUGENE CASSIDY
HVAC-Rough 5/2/2024 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 5/2/2024 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 5/2/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/14/2024 Approved EUGENE CASSIDY
HVAC-Rough 5/14/2024 Partial Approval EUGENE CASSIDY
Insulation 5/14/2024 Approved EUGENE CASSIDY
Drywall Nailing 6/17/2024 Approved JAMES CHAVEZ
HVAC-Rough 6/17/2024 Approved JAMES CHAVEZ
Shower Pan 6/17/2024 Corrections Issued JAMES CHAVEZ
Shower Pan 6/28/2024 Approved EUGENE CASSIDY
Underground Mechanical 8/16/2024 Corrections Issued EUGENE CASSIDY
Gas Test 8/19/2024 Not Ready for Inspection EUGENE CASSIDY
Sewer 8/19/2024 Approved EUGENE CASSIDY
Underground Mechanical 8/19/2024 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 9/4/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 11/12/2024 Not Ready for Inspection EUGENE CASSIDY
Final 11/12/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 11/12/2024 Approved EUGENE CASSIDY
Green Building Final 11/12/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 11/12/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 11/12/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 11/12/2024 Approved EUGENE CASSIDY
PLUMBING-Final 11/12/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/12/2024 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 11/12/2024 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 11/12/2024 Not Ready for Inspection EUGENE CASSIDY
Final 12/16/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 12/16/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 12/16/2024 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 12/16/2024 Approved EUGENE CASSIDY
Final 2/14/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 2/14/2025 Approved EUGENE CASSIDY
Service/Power Release 2/14/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 4/30/2025 Approved EUGENE CASSIDY
Final 4/30/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 4/30/2025 Approved EUGENE CASSIDY
PLUMBING-Final 4/30/2025 Approved EUGENE CASSIDY
Service/Power Release 4/30/2025 Approved EUGENE CASSIDY