609 1/2 W F ST 90744

Certificate Information: 609 1/2 W F ST 90744

Application / Permit
23010-40000-01558
Plan Check / Job No.
B23SP00059
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY A.D.U. PER ORDINANCE BETWEEN (E) GARAGE/WASH ROOM AND APARTMENT.
Permit Issued
Issued on 5/23/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 8/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2023 APPLICANT
Assigned to Plan Check Engineer 4/17/2023 LAWRENCE QUIRANTE
Corrections Issued 4/17/2023 LAWRENCE QUIRANTE
Plan Check Approved 5/18/2023 SERGIO SILVA
Issued 5/23/2023 APPLICANT
CofO in Progress 8/28/2024 EUGENE CASSIDY
CofO Issued 8/30/2024 ANSON MAGLASANG
Permit Finaled 8/30/2024 ANSON MAGLASANG

Permit Application Clearance Information

"Q" conditions Cleared 4/19/2023 DANIEL CORONADO
Address approval Cleared 4/24/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 4/24/2023 ANA SORIANO
Sewer availability Cleared 4/24/2023 ANA SORIANO
Low Impact Development (LID) Cleared 5/16/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 5/18/2023 ANA SORIANO

Contact Information

Contractor Hilltop Design-Build Inc; Lic. No.: 969696-B 1441 W 7TH STREET 2ND FLOOR      SAN PEDRO, CA 90732
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/21/2023 Approved EUGENE CASSIDY
METHANE-Barrier 6/21/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 6/21/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 7/11/2023 Partial Approval EUGENE CASSIDY
Wood Frame 7/11/2023 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 8/18/2023 Partial Approval EUGENE CASSIDY
Gas Test 8/18/2023 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 8/18/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/15/2023 Approved EUGENE CASSIDY
Green Building Rough 9/15/2023 Approved EUGENE CASSIDY
Insulation 9/15/2023 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/15/2023 Partial Approval EUGENE CASSIDY
METHANE-Rough 9/15/2023 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 9/15/2023 Approved EUGENE CASSIDY
Drywall Nailing 9/25/2023 Approved EUGENE CASSIDY
Final 2/20/2024 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 2/20/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 2/20/2024 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 2/20/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Not Ready EUGENE CASSIDY
Final 4/18/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 4/18/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 4/18/2024 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/18/2024 Approved EUGENE CASSIDY
Final 8/21/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 8/21/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/21/2024 SGSOV Approved EUGENE CASSIDY
Service/Power Release 8/21/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 8/26/2024 Approved EUGENE CASSIDY
Final 8/26/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 8/26/2024 Approved EUGENE CASSIDY
PLUMBING-Final 8/26/2024 Approved EUGENE CASSIDY
Service/Power Release 8/28/2024 Approved EUGENE CASSIDY