6702 N KESTER AVE 91405
Certificate Information: 6702 N KESTER AVE 91405
- Application / Permit
- 23010-30000-05190
- Plan Check / Job No.
- B23WL03138
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 3-story SFD at middle of the lot
- Permit Issued
- Issued on 8/2/2024
- Issuing Office
- Current Status
- CofO Issued on 7/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2024 | REZA HAGHIGHAT |
| Corrections Issued | 1/6/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 1/12/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 1/12/2024 | APPLICANT |
| Plan Check Approved | 3/29/2024 | REZA HAGHIGHAT |
| Issued | 8/2/2024 | APPLICANT |
| CofO in Progress | 7/2/2025 | RYAN SALAZAR |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
| CofO Issued | 7/10/2025 | RUBEN SALAS |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2024 | EDGAR ALCARAZ |
| "Q" conditions | Cleared | 1/12/2024 | ALEX VELA |
| CPC | Cleared | 1/12/2024 | ALEX VELA |
| Frnt yard landscape/Water mgmt | Cleared | 1/12/2024 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/29/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 2/9/2024 | LAVEON RIDER |
| Low Impact Development | Cleared | 2/20/2024 | SAMUEL LINN |
| Highway dedication | Cleared | 2/28/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 2/28/2024 | EDGAR ALCARAZ |
| SB8 RUD | Cleared | 6/26/2024 | SAMANTHA RIVERA |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/19/2024 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 8/28/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 12/2/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 12/2/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/3/2024 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 12/3/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 12/3/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 12/3/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/10/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 12/10/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 12/10/2024 | Approved | RYAN SALAZAR |
| Insulation | 12/16/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/16/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 12/27/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/27/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 12/27/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 3/10/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 4/14/2025 | Approved | RYAN SALAZAR |
| HVAC-Final | 4/30/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 4/30/2025 | Approved | RYAN SALAZAR |
| Final | 6/30/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 6/30/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 6/30/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 6/30/2025 | Approved | RYAN SALAZAR |