10453 W SANDAL LANE 90077
Certificate Information: 10453 W SANDAL LANE 90077
- Application / Permit
- 23010-30000-05180
- Plan Check / Job No.
- B23WL03134
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1 STORY SFD WITH ATTACHED GARAGE AND BASEMENT ** see comments ** 1 OF 4 **
- Permit Issued
- Issued on 4/22/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2024 | KAVIAN REFAHI |
| Corrections Issued | 1/6/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 1/16/2024 | APPLICANT |
| Quality Review Completed | 1/17/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 6/14/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/16/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 12/20/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 3/28/2025 | KAVIAN REFAHI |
| Plan Check Approved | 4/21/2025 | KAVIAN REFAHI |
| Issued | 4/22/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/2/2024 | GILBERT URREA |
| Address approval | Cleared | 3/29/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 3/29/2024 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 3/29/2024 | BRENDEN HAWK |
| Permit | Cleared | 3/29/2024 | BRENDEN HAWK |
| Excavation more than 5-ft deep | Cleared | 6/14/2024 | CALOSHA APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | DARIN LAM |
| Sewer availability | Cleared | 7/25/2024 | DARIN LAM |
| ZA Case | Cleared | 8/6/2024 | JAZMIN ROQUE |
| BHO/Hillside ordinance | Cleared | 8/21/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 8/21/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 8/21/2024 | DINAH GARIN |
| Work Adjacent to Public Way | Cleared | 9/3/2024 | LIAM ODONOVAN |
| Low Impact Development (LID) | Cleared | 9/19/2024 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/20/2024 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 12/20/2024 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 12/20/2024 | KAVIAN REFAHI |
| Disturb/Remove Protected Trees | Cleared | 4/21/2025 | ADALBERTO VERA |
| Trees in Parkway | Cleared | 4/21/2025 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Masterman,, Gary Clyde; Lic. No.: GE567 | 1766 EAGLE RIDGE CIR WICHITA FALLS, TX 76309 |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 6/9/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 6/16/2025 | Partial Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 6/16/2025 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 6/17/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/1/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/2/2025 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/3/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 7/11/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 7/17/2025 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/17/2025 | Partial Approval | STEPHANIE SWANSON |
| Deputy Shotcrete | 7/18/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 8/4/2025 | Conditional Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/5/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/5/2025 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 8/6/2025 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 8/7/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 8/29/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 9/3/2025 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 9/4/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 9/19/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 9/19/2025 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 9/22/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 9/26/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 9/29/2025 | No Access for Inspection | CHRISTOPHER WILSON |
| Deputy Shotcrete | 9/30/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 9/30/2025 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 10/3/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 10/21/2025 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 12/2/2025 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 12/2/2025 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 12/4/2025 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 12/4/2025 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 12/15/2025 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 12/15/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 1/5/2026 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 1/7/2026 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 1/30/2026 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 4/13/2026 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2026 | Partial Approval | CHRISTOPHER WILSON |
| Wood Frame | 4/13/2026 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 4/28/2026 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/28/2026 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 5/6/2026 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 5/6/2026 | Partial Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 5/12/2026 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/14/2026 | Conditional Approval | RYAN SALAZAR |
| Deputy Wood Construction | 5/18/2026 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/19/2026 | Approved | DAVID SCANTLIN |
| Green Building Rough | 5/19/2026 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 5/19/2026 | Approved | DAVID SCANTLIN |
| Wood Frame | 5/19/2026 | Approved | DAVID SCANTLIN |
| Insulation | 6/2/2026 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/22/2026 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 6/29/2026 | Approved | RYAN SALAZAR |
| Shower Pan | 7/16/2026 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/20/2026 | Approved | DAVID SCANTLIN |