1312 N FULLER AVE 1 - 3 90046
Certificate Information: 1312 N FULLER AVE 1 - 3 90046
- Application / Permit
- 23010-30000-04801
- Plan Check / Job No.
- B23WL02935
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-story duplex w./ roof decks and att. 2-car garage and att. ADU at rear of the lot per LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- Current Status
- Issued on 4/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | REZA HAGHIGHAT |
| Corrections Issued | 12/10/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 12/14/2023 | KAVIAN REFAHI |
| Disabled Access Plans Picked Up | 1/2/2024 | APPLICANT |
| Plan Check Approved | 2/28/2024 | REZA HAGHIGHAT |
| Issued | 4/18/2024 | APPLICANT |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 12/12/2023 | ASHLEY RODARTE |
| Low Impact Development (LID) | Cleared | 12/21/2023 | SAMUEL LINN |
| Address approval | Cleared | 12/22/2023 | CELINA MORENO |
| Highway dedication | Cleared | 12/22/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2023 | CELINA MORENO |
| Sewer availability | Cleared | 12/27/2023 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 1/30/2024 | KURT CORRAL |
| DAS Clearance | Cleared | 2/1/2024 | SHINE LIN |
| SB8 RUD | Cleared | 2/23/2024 | CHARLOTTE KINGS |
| Roof/Waste drainage to street | Cleared | 2/26/2024 | STEVE MELGAR |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Residential Alchemists; Lic. No.: 1098394-B | 2088 S ATLANTIC BLVD #276 MONTEREY PARK, CA 91754 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/12/2024 | Approved | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/22/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 7/24/2024 | Corrections Issued | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 7/25/2024 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/25/2024 | Corrections Issued | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 7/30/2024 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 1/24/2025 | No Access for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 1/24/2025 | No Access for Inspection | ROY SPAULDING |
| Green Building Rough | 1/24/2025 | No Access for Inspection | ROY SPAULDING |
| HVAC-Rough | 1/24/2025 | No Access for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 1/24/2025 | No Access for Inspection | ROY SPAULDING |
| Shower Pan | 1/24/2025 | No Access for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 1/24/2025 | No Access for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 2/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 2/4/2025 | Partial Approval | ROY SPAULDING |
| PLUMBING-Rough | 2/4/2025 | Corrections Issued | ROY SPAULDING |
| ELECTRICAL-Rough | 2/5/2025 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2025 | Approved | ROY SPAULDING |
| HVAC-Rough | 2/5/2025 | Partial Approval | ROY SPAULDING |
| PLUMBING-Rough | 2/5/2025 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 3/13/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 3/13/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 3/17/2025 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 3/17/2025 | Not Ready for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 3/17/2025 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 3/18/2025 | Conditional Approval | ROY SPAULDING |
| Green Building Rough | 3/18/2025 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 3/18/2025 | Approved | ROY SPAULDING |
| Insulation | 3/25/2025 | Corrections Issued | BRENDAN MORELLI |
| Drywall Nailing | 5/1/2025 | Approved | ROY SPAULDING |
| Shower Pan | 6/10/2025 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 7/16/2025 | Approved | ROY SPAULDING |
| Sewer | 7/31/2025 | Approved | BRIAN SULLIVAN |