13216 W OLD OAK LANE 90049

Certificate Information: 13216 W OLD OAK LANE 90049

Application / Permit
23010-30000-04493
Plan Check / Job No.
B23WL02797
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD WITH BASEMENT AND ATTACHED 3 CAR GARAGE ---1 OF 4---
Permit Issued
Issued on 10/17/2024
Issuing Office
West Los Angeles
Current Status
Issued on 10/17/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/8/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 KAVIAN REFAHI
Corrections Issued 11/24/2023 KAVIAN REFAHI
Quality Review Completed 11/29/2023 REZA HAGHIGHAT
Building Plans Picked Up 12/4/2023 APPLICANT
Applicant returned to address corrections 3/4/2024 KAVIAN REFAHI
Applicant returned to address corrections 5/29/2024 KAVIAN REFAHI
Applicant returned to address corrections 5/31/2024 KAVIAN REFAHI
Applicant returned to address corrections 8/26/2024 KAVIAN REFAHI
Applicant returned to address corrections 10/2/2024 KAVIAN REFAHI
Plan Check Approved 10/8/2024 KAVIAN REFAHI
Issued 10/17/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/8/2023 VLADIMIR ARUTYUNYAN
BHO/Hillside ordinance Cleared 12/13/2023 BRENDEN HAWK
BHO/Hillside ordinance Cleared 12/13/2023 BRENDEN HAWK
BHO/Hillside ordinance Cleared 12/13/2023 BRENDEN HAWK
BHO/Hillside ordinance Cleared 12/13/2023 BRENDEN HAWK
Miscellaneous Cleared 12/15/2023 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 1/16/2024 BRENDEN HAWK
Trees in Parkway Cleared 3/21/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 7/8/2024 KURT CORRAL
Permit Cleared 7/24/2024 DARIN LAM
GPI Written Notices Cleared 8/26/2024 KAVIAN REFAHI
Grading Pre-Inspection Cleared 8/26/2024 KAVIAN REFAHI
Low Impact Development (LID) Cleared 9/11/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 9/13/2024 DARIN LAM
Excavation more than 5-ft deep Cleared 10/2/2024 CALOSHA APPROVED
Private sewage disp. approval Cleared 10/4/2024 DAN RYAN EVANGELISTA

Contact Information

Contractor Tyler Development Corporation; Lic. No.: 451882-B 1932 COTNER AVE      LOS ANGELES, CA 90025
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Geologist Irvine,, Jon Alan; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/15/2024 No Access for Inspection KEVIN SARGSYAN
Pre-Inspection 11/18/2024 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/8/2025 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 4/17/2025 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 4/18/2025 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 5/7/2025 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 5/22/2025 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 5/22/2025 Partial Approval KEVIN SARGSYAN
Pre-Inspection 6/4/2025 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 6/16/2025 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 6/18/2025 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 7/17/2025 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 8/5/2025 Partial Approval HERBERT GIRON
Deputy Reinf. Concrete 8/6/2025 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 8/14/2025 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 8/28/2025 Partial Approval HERBERT GIRON
Sewer 8/29/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 9/4/2025 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Partial Approval TEMISTOCLES CAAL
Sewer 9/9/2025 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 9/18/2025 Partial Approval KEVIN SARGSYAN
Structural Steel Frame 9/18/2025 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 9/30/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 10/10/2025 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 10/21/2025 Partial Approval HERBERT GIRON
Deputy Reinf. Concrete 10/22/2025 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 11/12/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/25/2026 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 4/27/2026 Partial Approval EVAN COOPER
PLUMBING-Rough 7/16/2026 Corrections Issued KEVIN SARGSYAN