2034 S GLYNDON AVE 90291
Certificate Information: 2034 S GLYNDON AVE 90291
- Application / Permit
- 23010-30000-04486
- Plan Check / Job No.
- B23WL02793
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-story detached garage & ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d),(g)
- Permit Issued
- Issued on 12/20/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 11/13/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 11/14/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 11/16/2023 | APPLICANT |
| Plan Check Approved | 12/20/2023 | HOOMAN HAJIZADEH |
| Issued | 12/20/2023 | APPLICANT |
| CofO in Progress | 12/31/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
| CofO Issued | 12/31/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2023 | DARIN LAM |
| Sewer availability | Cleared | 11/14/2023 | DARIN LAM |
| Specific Plan | Cleared | 11/14/2023 | ALESSANDRO MERCURI |
| Low Impact Development (LID) | Cleared | 12/12/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 12/19/2023 | DARIN LAM |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/11/2024 | Partial Inspection | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 4/11/2024 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 4/11/2024 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 4/11/2024 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 4/18/2024 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 4/25/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Corrections Issued | HERBERT GIRON |
| Deputy Drilled-In Anchors | 6/28/2024 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Approved | HERBERT GIRON |
| Underground Mechanical | 7/3/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 7/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 7/12/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/23/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 7/23/2024 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 7/23/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 7/29/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/5/2024 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 8/5/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 9/5/2024 | Partial Approval | HERBERT GIRON |
| Shower Pan | 9/5/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | HERBERT GIRON |
| Green Building Rough | 9/6/2024 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 9/6/2024 | Approved | HERBERT GIRON |
| Insulation | 9/16/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/16/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 9/25/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 11/27/2024 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 12/2/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/2/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/4/2024 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 12/4/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/6/2024 | Approved | HERBERT GIRON |
| Final | 12/6/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 12/6/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/6/2024 | SGSOV Not Required | HERBERT GIRON |
| Service/Power Release | 12/24/2024 | Approved | KENNETH NAGLE |
| Final | 12/30/2024 | OK to Issue CofO | TEMISTOCLES CAAL |