115-115 1/2 E 116TH PL 90061

Certificate Information: 115-115 1/2 E 116TH PL 90061

Application / Permit
23010-30000-03978
Plan Check / Job No.
B23WL02499
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
new 2-story Duplex *** 1 of 2 ***
Permit Issued
Issued on 3/12/2024
Issuing Office
South Los Angeles
Current Status
CofO Issued on 1/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 KAVIAN REFAHI
Corrections Issued 10/7/2023 KAVIAN REFAHI
Quality Review Completed 10/19/2023 REZA HAGHIGHAT
Building Plans Picked Up 10/23/2023 APPLICANT
Applicant returned to address corrections 2/22/2024 KAVIAN REFAHI
Plan Check Approved 3/11/2024 KAVIAN REFAHI
Issued 3/12/2024 APPLICANT
CofO in Progress 1/27/2025 ANTHONY EGSON
CofO Issued 1/29/2025 ANSON MAGLASANG
Permit Finaled 1/29/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/29/2023 ADRIAN SANCHEZ
Permit Cleared 11/29/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 12/13/2023 ADRIAN SANCHEZ
Sewer availability Cleared 12/13/2023 ADRIAN SANCHEZ
Trees in Parkway Cleared 12/20/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 1/26/2024 JOHN CONNEALLY
Low Impact Development (LID) Cleared 2/7/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 2/9/2024 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/21/2024 Approved BEN MOLSTAD
Footing/Foundation/Slab 3/21/2024 Partial Approval BEN MOLSTAD
METHANE-Barrier 3/21/2024 Partial Approval BEN MOLSTAD
METHANE-Subgrade 3/21/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Partial Approval JAMES CHAVEZ
PLUMBING-Rough 4/3/2024 Partial Approval JAMES CHAVEZ
Underground Mechanical 4/3/2024 Not Ready for Inspection JAMES CHAVEZ
Insulation 4/4/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 5/6/2024 Approved JAMES CHAVEZ
PLUMBING-Rough 5/6/2024 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 5/7/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 5/7/2024 Corrections Issued BEN MOLSTAD
Green Building Rough 5/7/2024 Not Ready for Inspection BEN MOLSTAD
MERV13>=Rough 5/7/2024 Approved BEN MOLSTAD
METHANE-Rough 5/7/2024 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 5/7/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 5/10/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 5/10/2024 Corrections Issued BEN MOLSTAD
Green Building Rough 5/10/2024 Approved BEN MOLSTAD
METHANE-Rough 5/10/2024 Not Ready for Inspection BEN MOLSTAD
Underground Mechanical 5/10/2024 Partial Approval BEN MOLSTAD
Verify Sprinkler Sign Off 5/10/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 5/14/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 5/14/2024 Approved JAMES CHAVEZ
METHANE-Rough 5/14/2024 Approved JAMES CHAVEZ
PLUMBING-Rough 5/14/2024 Approved JAMES CHAVEZ
Underground Mechanical 5/14/2024 Partial Approval JAMES CHAVEZ
Verify Sprinkler Sign Off 5/14/2024 Approved JAMES CHAVEZ
Insulation 5/17/2024 Approved BEN MOLSTAD
Drywall Nailing 5/21/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 5/21/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 5/29/2024 Partial Approval BEN MOLSTAD
ELECTRICAL-Final 10/16/2024 Corrections Issued BARRY HACHE
HVAC-Final 10/16/2024 Approved BARRY HACHE
Sewer 11/22/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 11/27/2024 Corrections Issued ANTHONY EGSON
Final 11/27/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 11/27/2024 Partial Approval ANTHONY EGSON
Green Building Final 11/27/2024 Approved ANTHONY EGSON
HVAC-Final 11/27/2024 Corrections Issued ANTHONY EGSON
MERV13>=Final 11/27/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 11/27/2024 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Required ANTHONY EGSON
Service/Power Release 11/27/2024 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 11/27/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 1/3/2025 No Access for Inspection TEMISTOCLES CAAL
Final 1/3/2025 No Access for Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 1/3/2025 No Access for Inspection TEMISTOCLES CAAL
MERV13>=Final 1/3/2025 No Access for Inspection TEMISTOCLES CAAL
METHANE-Barrier 1/3/2025 No Access for Inspection TEMISTOCLES CAAL
METHANE-Subgrade 1/3/2025 No Access for Inspection TEMISTOCLES CAAL
PLUMBING-Final 1/3/2025 No Access for Inspection TEMISTOCLES CAAL
Service/Power Release 1/3/2025 No Access for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 1/9/2025 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 1/9/2025 Approved ANTHONY EGSON
PLUMBING-Final 1/9/2025 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 1/9/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 1/15/2025 Approved ANTHONY EGSON
Final 1/15/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Final 1/15/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/27/2025 Approved ANTHONY EGSON
Final 1/27/2025 OK to Issue CofO ANTHONY EGSON
Green Building Rough 1/27/2025 Approved ANTHONY EGSON