3209 W 18TH ST #3 90019
Certificate Information: 3209 W 18TH ST #3 90019
- Application / Permit
- 23010-30000-03910
- Plan Check / Job No.
- B23WL02446
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story ADU at rear of the lot per CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/6/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2023 | REZA HAGHIGHAT |
| Corrections Issued | 10/7/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 10/12/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 10/12/2023 | APPLICANT |
| Plan Check Approved | 1/24/2024 | REZA HAGHIGHAT |
| Issued | 2/6/2024 | APPLICANT |
| CofO in Progress | 8/18/2025 | WILLIAM SIERRA |
| Permit Finaled | 8/21/2025 | DEROLD HAUFF |
| CofO Issued | 8/21/2025 | DEROLD HAUFF |
| Permit Finaled | 8/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| SB8 RUD | Cleared | 10/6/2023 | MARY ARCENA |
| Address approval | Cleared | 10/17/2023 | WALLIE JONG |
| Highway dedication | Cleared | 10/17/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2023 | WALLIE JONG |
| Sewer availability | Cleared | 10/18/2023 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 10/19/2023 | JOE TAM |
| Hydrant and Access approval | Cleared | 10/23/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 10/30/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 10/31/2023 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 11/14/2023 | ISAIAH ROSS |
| Construction near power lines | Cleared | 1/19/2024 | RIDWAN HARDY |
Contact Information
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 15831 SAN JOSE AVE LA PUENTE, CA 91744 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 3/28/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 3/28/2024 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 4/11/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 4/11/2024 | Approved | ARTHUR NEGRETE |
| Sewer | 4/22/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 7/19/2024 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 8/20/2024 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Rough | 8/21/2024 | Corrections Issued | WILLIAM SIERRA |
| METHANE-Rough | 8/21/2024 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 8/27/2024 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 8/27/2024 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 9/16/2024 | Corrections Issued | WILLIAM SIERRA |
| Green Building Rough | 9/16/2024 | Approved | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 9/16/2024 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 9/18/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | WILLIAM SIERRA |
| Insulation | 9/25/2024 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 9/25/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Drywall Nailing | 10/7/2024 | Corrections Issued | WILLIAM SIERRA |
| Interior/Exterior Lathing | 10/7/2024 | Approved | WILLIAM SIERRA |
| Pre-Inspection | 10/9/2024 | Corrections Issued | WILLIAM SIERRA |
| Reinforced Concrete Frame | 10/9/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Special/Order Compliance | 10/9/2024 | Corrections Issued | WILLIAM SIERRA |
| Drywall Nailing | 10/11/2024 | Corrections Issued | WILLIAM SIERRA |
| Special/Order Compliance | 10/11/2024 | Corrections Issued | WILLIAM SIERRA |
| Shower Pan | 10/15/2024 | Corrections Issued | WILLIAM SIERRA |
| Special/Order Compliance | 10/15/2024 | Approved | WILLIAM SIERRA |
| Pre-Inspection | 10/16/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Drywall Nailing | 10/17/2024 | Partial Approval | ANTHONY RAMOS |
| Underground Mechanical | 1/24/2025 | Approved | WILLIAM SIERRA |
| HVAC-Final | 5/6/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| PLUMBING-Final | 5/6/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| ELECTRICAL-Final | 6/16/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 6/16/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 6/16/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Final | 7/2/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Final | 7/2/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 7/2/2025 | Corrections Issued | WILLIAM SIERRA |
| Service/Power Release | 7/2/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 7/9/2025 | SGSOV Not Ready | WILLIAM SIERRA |
| Drywall Nailing | 7/14/2025 | Approved | WILLIAM SIERRA |
| Final | 7/14/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 7/14/2025 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Not Required | WILLIAM SIERRA |
| Service/Power Release | 7/14/2025 | Approved | WILLIAM SIERRA |
| Smoke Detectors | 7/14/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 7/18/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 7/18/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 7/18/2025 | Approved | WILLIAM SIERRA |
| Final | 7/25/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 7/25/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 7/29/2025 | Conditional Approval | ARTHUR NEGRETE |
| Green Building Final | 7/29/2025 | Approved | ARTHUR NEGRETE |
| Final | 8/11/2025 | OK to Issue CofO | WILLIAM SIERRA |
| Service/Power Release | 8/11/2025 | Approved | WILLIAM SIERRA |