2227 1-3 S AMHERST AVE 90064

Certificate Information: 2227 1-3 S AMHERST AVE 90064

Application / Permit
23010-30000-03776
Plan Check / Job No.
B23WL02349
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-story Duplex with roof decks, attached garage, and ADU per ordinance 12.22 A.33(c) and (e) (in rear of the lot)
Permit Issued
Issued on 3/26/2024
Issuing Office
Metro
Current Status
Issued on 3/26/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/19/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 HOOMAN HAJIZADEH
Corrections Issued 9/26/2023 HOOMAN HAJIZADEH
Quality Review Completed 10/3/2023 KAVIAN REFAHI
Building Plans Picked Up 10/6/2023 APPLICANT
Disabled Access Plans Picked Up 10/6/2023 APPLICANT
Applicant returned to address corrections 1/26/2024 HOOMAN HAJIZADEH
Plan Check Approved 2/2/2024 HOOMAN HAJIZADEH
Issued 3/26/2024 APPLICANT

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 10/2/2023 JOE TAM
Address approval Cleared 10/10/2023 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 10/12/2023 LIAM ODONOVAN
SB8 RUD Cleared 10/13/2023 BLAKE BOULIGNY
Hydrant and Access approval Cleared 10/16/2023 KURT CORRAL
Highway dedication Cleared 10/17/2023 DINAH GARIN
Sewer availability Cleared 10/23/2023 LIAM ODONOVAN
Specific Plan Cleared 11/5/2023 EDUARDO HERMOSO
Specific Plan Cleared 11/5/2023 EDUARDO HERMOSO
Low Impact Development (LID) Cleared 11/13/2023 ROGELIO CORTES
Trees in Parkway Cleared 11/13/2023 ADALBERTO VERA
Roof/Waste drainage to street Cleared 11/16/2023 LIAM ODONOVAN
Construction near power lines Cleared 11/21/2023 RIDWAN HARDY
Permit Cleared 11/27/2023 DINAH GARIN
DAS Clearance Cleared 12/14/2023 SHINE LIN
Specific Plan Cleared 1/8/2024 JULISSA LOPEZ-HODOYAN
Miscellaneous Cleared 1/17/2024 DANIEL CORONADO
Miscellaneous Cleared 1/17/2024 DANIEL CORONADO
Miscellaneous Cleared 1/17/2024 DANIEL CORONADO
Building over 36-ft Cleared 1/26/2024 CALOSHA APPROVED

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Precision General Construction Inc; Lic. No.: 1030555-B 1323 W MALBORO AVENUE      ANAHEIM, CA 92801
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Haddad,, Raymond M; Lic. No.: GE2985 17106 CEREDO PL      GRANADA HILLS, CA 91344
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/9/2024 Partial Approval KIRK SANDERS
Sewer 8/5/2024 Corrections Issued KIRK SANDERS
Underground Mechanical 8/8/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 9/4/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 9/4/2024 Conditional Approval KIRK SANDERS
Special/Order Compliance 9/4/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 10/2/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Conditional Approval KIRK SANDERS
Structural Steel Frame 1/17/2025 Corrections Issued KIRK SANDERS
Pre-Inspection 5/5/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Partial Approval ARAM AVEDISIAN
HVAC-Rough 9/16/2025 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 9/17/2025 Approved ARAM AVEDISIAN
Final 9/22/2025 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 10/27/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 10/31/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 11/4/2025 Corrections Issued MICHAEL ALLEN
Deputy Wood Construction 11/4/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 11/4/2025 Approved MICHAEL ALLEN
Green Building Rough 11/4/2025 Conditional Approval MICHAEL ALLEN
MERV13>=Rough 11/4/2025 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 11/4/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 11/14/2025 Approved MICHAEL ALLEN
Green Building Rough 11/14/2025 Approved MICHAEL ALLEN
Insulation 11/14/2025 Corrections Issued MICHAEL ALLEN
Interior/Exterior Lathing 11/14/2025 Partial Approval MICHAEL ALLEN
Interior/Exterior Lathing 11/20/2025 Approved MICHAEL ALLEN
Shower Pan 11/20/2025 Approved MICHAEL ALLEN
Insulation 12/1/2025 Corrections Issued MICHAEL ALLEN
Insulation 12/9/2025 Corrections Issued MICHAEL ALLEN
Insulation 12/15/2025 Approved MICHAEL ALLEN
Drywall Nailing 1/7/2026 Partial Approval DANIEL VERA
Drywall Nailing 1/12/2026 Approved MICHAEL ALLEN
Special/Order Compliance 4/6/2026 Approved JUAN VALENZUELA