2227 1-3 S AMHERST AVE 90064
Certificate Information: 2227 1-3 S AMHERST AVE 90064
- Application / Permit
- 23010-30000-03776
- Plan Check / Job No.
- B23WL02349
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-story Duplex with roof decks, attached garage, and ADU per ordinance 12.22 A.33(c) and (e) (in rear of the lot)
- Permit Issued
- Issued on 3/26/2024
- Issuing Office
- Metro
- Current Status
- Issued on 3/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 9/26/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 10/3/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 10/6/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 10/6/2023 | APPLICANT |
| Applicant returned to address corrections | 1/26/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 2/2/2024 | HOOMAN HAJIZADEH |
| Issued | 3/26/2024 | APPLICANT |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 10/2/2023 | JOE TAM |
| Address approval | Cleared | 10/10/2023 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2023 | LIAM ODONOVAN |
| SB8 RUD | Cleared | 10/13/2023 | BLAKE BOULIGNY |
| Hydrant and Access approval | Cleared | 10/16/2023 | KURT CORRAL |
| Highway dedication | Cleared | 10/17/2023 | DINAH GARIN |
| Sewer availability | Cleared | 10/23/2023 | LIAM ODONOVAN |
| Specific Plan | Cleared | 11/5/2023 | EDUARDO HERMOSO |
| Specific Plan | Cleared | 11/5/2023 | EDUARDO HERMOSO |
| Low Impact Development (LID) | Cleared | 11/13/2023 | ROGELIO CORTES |
| Trees in Parkway | Cleared | 11/13/2023 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 11/16/2023 | LIAM ODONOVAN |
| Construction near power lines | Cleared | 11/21/2023 | RIDWAN HARDY |
| Permit | Cleared | 11/27/2023 | DINAH GARIN |
| DAS Clearance | Cleared | 12/14/2023 | SHINE LIN |
| Specific Plan | Cleared | 1/8/2024 | JULISSA LOPEZ-HODOYAN |
| Miscellaneous | Cleared | 1/17/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 1/17/2024 | DANIEL CORONADO |
| Miscellaneous | Cleared | 1/17/2024 | DANIEL CORONADO |
| Building over 36-ft | Cleared | 1/26/2024 | CALOSHA APPROVED |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Precision General Construction Inc; Lic. No.: 1030555-B | 1323 W MALBORO AVENUE ANAHEIM, CA 92801 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/9/2024 | Partial Approval | KIRK SANDERS |
| Sewer | 8/5/2024 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 8/8/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 9/4/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 9/4/2024 | Conditional Approval | KIRK SANDERS |
| Special/Order Compliance | 9/4/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 10/2/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Conditional Approval | KIRK SANDERS |
| Structural Steel Frame | 1/17/2025 | Corrections Issued | KIRK SANDERS |
| Pre-Inspection | 5/5/2025 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 9/16/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 9/17/2025 | Approved | ARAM AVEDISIAN |
| Final | 9/22/2025 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/27/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Rough | 10/31/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 11/4/2025 | Corrections Issued | MICHAEL ALLEN |
| Deputy Wood Construction | 11/4/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 11/4/2025 | Conditional Approval | MICHAEL ALLEN |
| MERV13>=Rough | 11/4/2025 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 11/4/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 11/14/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 11/14/2025 | Approved | MICHAEL ALLEN |
| Insulation | 11/14/2025 | Corrections Issued | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/14/2025 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/20/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 11/20/2025 | Approved | MICHAEL ALLEN |
| Insulation | 12/1/2025 | Corrections Issued | MICHAEL ALLEN |
| Insulation | 12/9/2025 | Corrections Issued | MICHAEL ALLEN |
| Insulation | 12/15/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 1/7/2026 | Partial Approval | DANIEL VERA |
| Drywall Nailing | 1/12/2026 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 4/6/2026 | Approved | JUAN VALENZUELA |