1658 S HAYWORTH AVE 90035
Certificate Information: 1658 S HAYWORTH AVE 90035
- Application / Permit
- 23010-30000-03718
- Plan Check / Job No.
- B23WL02330
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 2-story ADU (1861 sf ) ; (5-bedroom ; 5-bathroom) per GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)1, (d)1, and (g) LAMC 12.22 A.33(c)1, (d)1, and (g) at rear of the lot (bldg B)
- Permit Issued
- Issued on 1/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | YASHAR EMAMI |
| Corrections Issued | 9/26/2023 | YASHAR EMAMI |
| Quality Review Completed | 9/28/2023 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 12/7/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 1/12/2024 | YASHAR EMAMI |
| Plan Check Approved | 1/19/2024 | YASHAR EMAMI |
| Issued | 1/29/2024 | APPLICANT |
| CofO in Progress | 1/8/2026 | BRENDAN MORELLI |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| CofO Issued | 1/9/2026 | DEROLD HAUFF |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| SB8 RUD | Cleared | 9/26/2023 | KE ZHANG |
| Address approval | Cleared | 9/27/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2023 | KHAING AYE |
| Permit | Cleared | 9/27/2023 | KHAING AYE |
| Sewer availability | Cleared | 9/27/2023 | KHAING AYE |
| Construction near power lines | Cleared | 9/30/2023 | RIDWAN HARDY |
| Highway dedication | Cleared | 10/2/2023 | KHAING AYE |
| Hydrant and Access approval | Cleared | 10/20/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 11/14/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 11/20/2023 | JILVER MAZARIEGOS |
Contact Information
| Architect | Hamid, Dehghan; Lic. No.: C35150 | , |
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 15831 SAN JOSE AVE LA PUENTE, CA 91744 |
| Engineer | Aboufadel,, Nicholas Fadlo; Lic. No.: C50588 | 4000 PARK NEWPORT SUITE 303 NEWPORT BEACH, CA 92660 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 3/20/2024 | Approved | STUART CHAPMAN |
| Underground Mechanical | 3/20/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 3/21/2024 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 3/28/2024 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/28/2024 | Approved | STUART CHAPMAN |
| METHANE-Barrier | 3/28/2024 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | No Access for Inspection | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 7/30/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 7/30/2024 | Corrections Issued | JUSTIN HAWLEY |
| Special/Order Compliance | 7/30/2024 | Corrections Issued | JUSTIN HAWLEY |
| HVAC-Rough | 8/8/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Rough | 8/8/2024 | No Access for Inspection | ARTHUR NEGRETE |
| Special/Order Compliance | 8/8/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Special/Order Compliance | 8/8/2024 | Partial Approval | NICHOLAS LOPEZ |
| HVAC-Rough | 8/14/2024 | Not Ready for Inspection | SCOTT FINNILA |
| HVAC-Rough | 8/26/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 8/26/2024 | Approved | ARTHUR NEGRETE |
| Deputy Wood Construction | 9/10/2024 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 10/1/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 10/1/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 10/1/2024 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 10/1/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 10/16/2024 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 10/24/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 11/4/2024 | Approved | ARTHUR NEGRETE |
| Sewer | 4/4/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 11/20/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 11/20/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 11/20/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 11/20/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Final | 11/20/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Required | ARTHUR NEGRETE |
| Service/Power Release | 11/20/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 11/20/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 12/12/2025 | Corrections Issued | BRENDAN MORELLI |
| Service/Power Release | 12/12/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Smoke Detectors | 12/12/2025 | Approved | BRENDAN MORELLI |
| Final | 12/16/2025 | Conditional Approval | BRENDAN MORELLI |
| Green Building Final | 12/16/2025 | Approved | BRENDAN MORELLI |
| Service/Power Release | 12/16/2025 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 12/19/2025 | Corrections Issued | BRENDAN MORELLI |
| Final | 1/8/2026 | OK to Issue CofO | BRENDAN MORELLI |
| Service/Power Release | 1/8/2026 | Approved | BRENDAN MORELLI |