18762 W TUBA ST 91324
Certificate Information: 18762 W TUBA ST 91324
- Application / Permit
- 23010-30000-03696
- Plan Check / Job No.
- B23WL02319
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 49'-2" x 18'-2" DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/13/2023
- Issuing Office
- Valley
- Current Status
- Issued on 12/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | RICHARD GARCIA |
| Corrections Issued | 9/21/2023 | RICHARD GARCIA |
| Plan Check Approved | 12/8/2023 | MIROOSH KHACHATOORIAN |
| Issued | 12/13/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2023 | COLIN LOREDO |
| Permit | Cleared | 9/25/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 9/25/2023 | COLIN LOREDO |
| ZI | Cleared | 9/27/2023 | ASHLEY RODARTE |
| Low Impact Development (LID) | Cleared | 12/6/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 12/6/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/22/2024 | No Access for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 4/22/2024 | No Access for Inspection | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Underground Mechanical | 4/24/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 4/26/2024 | Partial Approval | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 6/3/2024 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 6/14/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 6/14/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Rough | 6/14/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| HVAC-Rough | 6/14/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 6/14/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Verify Sprinkler Sign Off | 6/14/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 6/20/2024 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 6/20/2024 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 6/20/2024 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 7/3/2024 | Partial Inspection | KRISTEN CAUSEY |
| Insulation | 7/29/2024 | Corrections Issued | DAVID SCANTLIN |
| Drywall Nailing | 8/6/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Green Building Rough | 8/6/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Drywall Nailing | 8/12/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 8/12/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 8/12/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 9/6/2024 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 1/24/2025 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 5/22/2025 | No Access for Inspection | DAVID SCANTLIN |
| Final | 5/22/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/22/2025 | No Access for Inspection | DAVID SCANTLIN |
| Green Building Final | 5/22/2025 | No Access for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2025 | SGSOV Not Ready | DAVID SCANTLIN |
| Service/Power Release | 5/22/2025 | No Access for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 5/22/2025 | No Access for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 5/22/2025 | No Access for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/29/2025 | Approved | DAVID SCANTLIN |
| Final | 5/29/2025 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/29/2025 | Approved | DAVID SCANTLIN |
| Green Building Final | 5/29/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 5/29/2025 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 5/29/2025 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 5/29/2025 | Approved | DAVID SCANTLIN |