18134 W SUPERIOR ST 91325

Certificate Information: 18134 W SUPERIOR ST 91325

Application / Permit
23010-30000-03671
Plan Check / Job No.
B23WL02309
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 10/12/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2023 APPLICANT
Assigned to Plan Check Engineer 9/19/2023 RICHARD GARCIA
Corrections Issued 9/19/2023 RICHARD GARCIA
Building Plans Picked Up 9/21/2023 APPLICANT
Plan Check Approved 10/12/2023 RICHARD GARCIA
Issued 10/12/2023 APPLICANT
CofO in Progress 5/10/2024 DAVID SCANTLIN
CofO in Progress 5/14/2024 JOHN JANSON
CofO in Progress 5/28/2024 DAVID SCANTLIN
CofO in Progress 7/24/2024 DAVID SCANTLIN
Permit Finaled 7/24/2024 JOHN JANSON
CofO Issued 7/24/2024 JOHN JANSON
Permit Finaled 7/24/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/22/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 9/22/2023 ROMAN GUTIERREZ
Sewer availability Cleared 9/22/2023 ROMAN GUTIERREZ
Low Impact Development (LID) Cleared 10/10/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 10/10/2023 COLIN LOREDO

Contact Information

Contractor Eurocon Group Inc; Lic. No.: 708010-B 923 HILTS AVE      LOS ANGELES, CA 90024
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/14/2023 Conditional Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Approved DAVID SCANTLIN
Deputy Wood Construction 1/9/2024 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 1/18/2024 Approved DAVID SCANTLIN
HVAC-Rough 1/18/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/18/2024 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 1/18/2024 Approved DAVID SCANTLIN
Shower Pan 1/18/2024 Approved DAVID SCANTLIN
Wood Frame 1/18/2024 Approved DAVID SCANTLIN
Insulation 1/22/2024 Partial Approval JOHN KIDWELL
Gas Test 1/25/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/25/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 1/25/2024 Approved DAVID SCANTLIN
Drywall Nailing 1/26/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/26/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 1/29/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 4/18/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 4/18/2024 Approved DAVID SCANTLIN
Final 4/18/2024 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 4/18/2024 Approved DAVID SCANTLIN
Green Building Final 4/18/2024 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 4/18/2024 Approved DAVID SCANTLIN
HVAC-Final 4/18/2024 Approved DAVID SCANTLIN
PLUMBING-Final 4/18/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Approved DAVID SCANTLIN
Service/Power Release 4/18/2024 Approved DAVID SCANTLIN
Smoke Detectors 4/18/2024 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 4/18/2024 Approved DAVID SCANTLIN
Final 5/3/2024 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 5/3/2024 Approved DAVID SCANTLIN
Final 5/10/2024 Not Ready for Inspection DAVID SCANTLIN
Special/Order Compliance 5/15/2024 Corrections Issued DAVID SCANTLIN
Final 7/24/2024 OK to Issue CofO DAVID SCANTLIN