701 N VENDOME ST 1 - 3 90026
Certificate Information: 701 N VENDOME ST 1 - 3 90026
- Application / Permit
- 23010-30000-03557
- Plan Check / Job No.
- B23WL02243
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-story duplex w./ att. 2-car garage and att. ADU (2,080 sf) and roof deck at rear of the lot per LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2023 | REZA HAGHIGHAT |
| Corrections Issued | 9/10/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 9/19/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 9/20/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 10/24/2023 | APPLICANT |
| Plan Check Approved | 1/2/2024 | REZA HAGHIGHAT |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 6/2/2025 | FREDDIE RIVERA |
| Permit Finaled | 6/3/2025 | DEROLD HAUFF |
| CofO Issued | 6/3/2025 | DEROLD HAUFF |
| Permit Finaled | 6/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| SB8 RUD | Cleared | 9/7/2023 | ALYSSA FLORES |
| Address approval | Cleared | 9/27/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 10/17/2023 | CHRISTINA BRACO |
| Frnt yard landscape/Water mgmt | Cleared | 10/19/2023 | RYAN LY |
| Hydrant and Access approval | Cleared | 10/25/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 10/25/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/25/2023 | CHRISTINA BRACO |
| DAS Clearance | Cleared | 11/9/2023 | REZA HAGHIGHAT |
| Highway dedication | Cleared | 12/29/2023 | TREVOR QUAN |
| GPI Written Notices | Cleared | 1/2/2024 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 1/2/2024 | REZA HAGHIGHAT |
| Hold | Cleared | 2/28/2024 | MARIA VENDIVIL |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/1/2024 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 3/15/2024 | Corrections Issued | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 3/18/2024 | Corrections Issued | FREDDIE RIVERA |
| Deputy Methane Barrier | 3/26/2024 | Partial Approval | JOSEPH MCGARRY |
| METHANE-Subgrade | 3/27/2024 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 3/29/2024 | Approved | RICHARD DOCKUS |
| METHANE-Subgrade | 3/29/2024 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 6/24/2024 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 7/11/2024 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Partial Approval | FREDDIE RIVERA |
| HVAC-Rough | 7/11/2024 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 7/11/2024 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 7/22/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/22/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/22/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/19/2024 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 8/19/2024 | Partial Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/19/2024 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 8/19/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 8/19/2024 | Conditional Approval | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 8/19/2024 | Approved | FREDDIE RIVERA |
| Wood Frame | 8/19/2024 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 8/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 8/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/27/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 8/27/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/27/2024 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 8/27/2024 | Approved | FREDDIE RIVERA |
| Wood Frame | 8/27/2024 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 9/3/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/3/2024 | Partial Approval | FREDDIE RIVERA |
| Shower Pan | 9/3/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/18/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/18/2024 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/4/2025 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 4/4/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/9/2025 | Approved | FREDDIE RIVERA |
| Final | 4/9/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/9/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 4/9/2025 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 4/9/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 4/9/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 4/9/2025 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 4/9/2025 | Approved | FREDDIE RIVERA |
| Structural Steel Frame | 4/9/2025 | Approved | FREDDIE RIVERA |
| Final | 4/30/2025 | Corrections Issued | FREDDIE RIVERA |
| Final | 5/7/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 5/7/2025 | Not Ready for Inspection | FREDDIE RIVERA |