644-644 1/2 N BOYLE AVE 90033
Certificate Information: 644-644 1/2 N BOYLE AVE 90033
- Application / Permit
- 23010-30000-03375
- Plan Check / Job No.
- B23WL02111
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- new 3-story Duplex (front) *** 1 of 3 ***
- Permit Issued
- Issued on 10/24/2023
- Issuing Office
- Current Status
- CofO Issued on 4/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | KAVIAN REFAHI |
| Corrections Issued | 8/27/2023 | KAVIAN REFAHI |
| Quality Review Completed | 9/5/2023 | CHIHARU SUZUKI |
| Plan Check Approved | 10/16/2023 | KAVIAN REFAHI |
| Issued | 10/24/2023 | APPLICANT |
| CofO in Progress | 4/29/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 4/30/2025 | DEROLD HAUFF |
| CofO Issued | 4/30/2025 | DEROLD HAUFF |
| Permit Finaled | 4/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2023 | JEANIE LAM |
| Highway dedication | Cleared | 9/1/2023 | JEANIE LAM |
| SB8 RUD | Cleared | 9/1/2023 | BLAKE BOULIGNY |
| Sewer availability | Cleared | 9/1/2023 | JEANIE LAM |
| Frnt yard landscape/Water mgmt | Cleared | 9/15/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/15/2023 | MAXFIELD VERMY |
| ZI | Cleared | 9/15/2023 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 9/24/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 9/26/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/28/2023 | JEANIE LAM |
| GPI Written Notices | Cleared | 10/16/2023 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 10/16/2023 | KAVIAN REFAHI |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | A-1 Steel Erector; Lic. No.: 931279-B | 9414 ZAMORA AVENUE LOS ANGELES, CA 90002 |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2023 | Partial Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 1/9/2024 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 1/11/2024 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 1/23/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 1/25/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 1/30/2024 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 6/10/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 6/10/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/30/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| ELECTRICAL-Rough | 8/1/2024 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 8/1/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/13/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/15/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 8/15/2024 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 8/15/2024 | Approved | OSVALDO PARAMO |
| METHANE-Rough | 8/15/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 8/15/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/19/2024 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Approved | OSVALDO PARAMO |
| Insulation | 8/26/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 9/5/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/9/2024 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 10/21/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 12/13/2024 | Partial Approval | OSVALDO PARAMO |
| Service/Power Release | 4/21/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/24/2025 | Partial Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Final | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/25/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/29/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |