913 N HOBART BLVD 90029
Certificate Information: 913 N HOBART BLVD 90029
- Application / Permit
- 23010-30000-03357
- Plan Check / Job No.
- B23WL02100
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 3-story SFD in front of the lot
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- Current Status
- CofO Issued on 4/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 8/31/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 9/12/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 11/3/2023 | HOOMAN HAJIZADEH |
| Plan Check Approved | 4/1/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 9/13/2024 | HOOMAN HAJIZADEH |
| Issued | 9/16/2024 | APPLICANT |
| CofO in Progress | 4/3/2026 | RAUL BARAJAS |
| Permit Finaled | 4/5/2026 | DEROLD HAUFF |
| CofO Issued | 4/5/2026 | DEROLD HAUFF |
| Permit Finaled | 4/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2023 | JESSICA OPINION |
| Highway dedication | Cleared | 9/1/2023 | JESSICA OPINION |
| Permit | Cleared | 9/1/2023 | JESSICA OPINION |
| SB8 RUD | Cleared | 9/6/2023 | NICHOLAS KAWAZOE |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 9/8/2023 | AHMED AMARRAGY |
| Frnt yard landscape/Water mgmt | Cleared | 9/26/2023 | SPENCER WEJROWSKI |
| Hydrant and Access approval | Cleared | 10/6/2023 | GILBERT URREA |
| Trees in Parkway | Cleared | 10/19/2023 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 1/23/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 1/25/2024 | JILVER MAZARIEGOS |
| Tenant Habitability Plan | Cleared | 2/20/2024 | RICARDO BOHORQUEZ |
Contact Information
| Architect | Hamid, Dehghan; Lic. No.: C35150 | 2355 WESTWOOD BLVD #900 LOS ANGELES, CA 90064 |
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 15831 SAN JOSE AVE LA PUENTE, CA 91744 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/8/2024 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 10/22/2024 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 2/20/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 3/4/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Rough | 3/4/2025 | Corrections Issued | WILLIAM SIERRA |
| Special/Order Compliance | 3/4/2025 | Corrections Issued | WILLIAM SIERRA |
| Deputy Wood Construction | 3/7/2025 | Conditional Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 3/10/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 3/18/2025 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 3/27/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/15/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 4/15/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 4/15/2025 | Not Ready for Inspection | JEFFREY MEAD |
| MERV13>=Rough | 4/15/2025 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 4/15/2025 | Approved | JEFFREY MEAD |
| Insulation | 4/24/2025 | Not Ready for Inspection | ALEX COLIN |
| Interior/Exterior Lathing | 4/24/2025 | Partial Approval | ALEX COLIN |
| Insulation | 4/29/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 5/14/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 5/14/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/12/2025 | Corrections Issued | JEFFREY MEAD |
| Shower Pan | 6/12/2025 | Corrections Issued | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/17/2025 | Not Ready for Inspection | JOSH MEISTER |
| Shower Pan | 6/17/2025 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 6/25/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 6/25/2025 | Approved | REGINA MENDEZ |
| Sewer | 8/5/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 8/15/2025 | Corrections Issued | JEFFREY MEAD |
| Service/Power Release | 12/19/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 1/30/2026 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Not Ready | JEFFREY MEAD |
| Service/Power Release | 1/30/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 1/30/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 2/11/2026 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/11/2026 | SGSOV Not Required | JEFFREY MEAD |
| Service/Power Release | 2/11/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 2/11/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 2/26/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 2/26/2026 | Approved | JEFFREY MEAD |
| MERV13>=Final | 2/26/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 2/26/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 2/26/2026 | Approved | JEFFREY MEAD |
| Final | 3/3/2026 | Corrections Issued | JEFFREY MEAD |
| Service/Power Release | 3/3/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 3/11/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 3/11/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 3/16/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Service/Power Release | 3/16/2026 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 3/26/2026 | Partial Inspection | JEFFREY MEAD |
| Service/Power Release | 3/26/2026 | Not Required | JEFFREY MEAD |
| Final | 4/3/2026 | OK to Issue CofO | RAUL BARAJAS |
| MERV13>=Final | 4/3/2026 | Approved | RAUL BARAJAS |