913 N HOBART BLVD 90029

Certificate Information: 913 N HOBART BLVD 90029

Application / Permit
23010-30000-03357
Plan Check / Job No.
B23WL02100
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story SFD in front of the lot
Permit Issued
Issued on 9/16/2024
Issuing Office
Current Status
CofO Issued on 4/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 HOOMAN HAJIZADEH
Corrections Issued 8/31/2023 HOOMAN HAJIZADEH
Quality Review Completed 9/12/2023 KAVIAN REFAHI
Applicant returned to address corrections 11/3/2023 HOOMAN HAJIZADEH
Plan Check Approved 4/1/2024 HOOMAN HAJIZADEH
Plan Check Approved 9/13/2024 HOOMAN HAJIZADEH
Issued 9/16/2024 APPLICANT
CofO in Progress 4/3/2026 RAUL BARAJAS
Permit Finaled 4/5/2026 DEROLD HAUFF
CofO Issued 4/5/2026 DEROLD HAUFF
Permit Finaled 4/5/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/1/2023 JESSICA OPINION
Highway dedication Cleared 9/1/2023 JESSICA OPINION
Permit Cleared 9/1/2023 JESSICA OPINION
SB8 RUD Cleared 9/6/2023 NICHOLAS KAWAZOE
Eng Process Fee Ord 176,300 Cleared 9/8/2023 AHMED AMARRAGY
Sewer availability Cleared 9/8/2023 AHMED AMARRAGY
Frnt yard landscape/Water mgmt Cleared 9/26/2023 SPENCER WEJROWSKI
Hydrant and Access approval Cleared 10/6/2023 GILBERT URREA
Trees in Parkway Cleared 10/19/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 1/23/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 1/25/2024 JILVER MAZARIEGOS
Tenant Habitability Plan Cleared 2/20/2024 RICARDO BOHORQUEZ

Contact Information

Architect Hamid, Dehghan; Lic. No.: C35150 2355 WESTWOOD BLVD   #900    LOS ANGELES, CA 90064
Contractor C S W F Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENTE, CA 91744
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/8/2024 Approved JEFFREY MEAD
Footing/Foundation/Slab 10/22/2024 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Approved JOHN QUINTANILLA
PLUMBING-Rough 2/20/2025 Approved JEFFREY MEAD
ELECTRICAL-Rough 3/4/2025 Corrections Issued WILLIAM SIERRA
HVAC-Rough 3/4/2025 Corrections Issued WILLIAM SIERRA
Special/Order Compliance 3/4/2025 Corrections Issued WILLIAM SIERRA
Deputy Wood Construction 3/7/2025 Conditional Approval JEFFREY MEAD
ELECTRICAL-Rough 3/10/2025 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Corrections Issued JEFFREY MEAD
HVAC-Rough 3/18/2025 Corrections Issued JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/27/2025 Approved JEFFREY MEAD
HVAC-Rough 3/27/2025 Approved JEFFREY MEAD
BUILDING-Rough-Frame 4/15/2025 Approved JEFFREY MEAD
Green Building Rough 4/15/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 4/15/2025 Not Ready for Inspection JEFFREY MEAD
MERV13>=Rough 4/15/2025 Approved JEFFREY MEAD
Verify Sprinkler Sign Off 4/15/2025 Approved JEFFREY MEAD
Insulation 4/24/2025 Not Ready for Inspection ALEX COLIN
Interior/Exterior Lathing 4/24/2025 Partial Approval ALEX COLIN
Insulation 4/29/2025 Approved RONNIE MINDANAO
Drywall Nailing 5/14/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 5/14/2025 Not Ready for Inspection JEFFREY MEAD
Interior/Exterior Lathing 6/12/2025 Corrections Issued JEFFREY MEAD
Shower Pan 6/12/2025 Corrections Issued JEFFREY MEAD
Interior/Exterior Lathing 6/17/2025 Not Ready for Inspection JOSH MEISTER
Shower Pan 6/17/2025 Not Ready for Inspection JOSH MEISTER
Interior/Exterior Lathing 6/25/2025 Approved REGINA MENDEZ
Shower Pan 6/25/2025 Approved REGINA MENDEZ
Sewer 8/5/2025 Approved JEFFREY MEAD
Underground Mechanical 8/15/2025 Corrections Issued JEFFREY MEAD
Service/Power Release 12/19/2025 Not Ready for Inspection JEFFREY MEAD
Final 1/30/2026 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Not Ready JEFFREY MEAD
Service/Power Release 1/30/2026 Not Ready for Inspection JEFFREY MEAD
Smoke Detectors 1/30/2026 Not Ready for Inspection JEFFREY MEAD
Final 2/11/2026 Corrections Issued JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 2/11/2026 SGSOV Not Required JEFFREY MEAD
Service/Power Release 2/11/2026 Not Ready for Inspection JEFFREY MEAD
Smoke Detectors 2/11/2026 Not Ready for Inspection JEFFREY MEAD
Final 2/26/2026 Not Ready for Inspection JEFFREY MEAD
Green Building Final 2/26/2026 Approved JEFFREY MEAD
MERV13>=Final 2/26/2026 Not Ready for Inspection JEFFREY MEAD
Service/Power Release 2/26/2026 Not Ready for Inspection JEFFREY MEAD
Smoke Detectors 2/26/2026 Approved JEFFREY MEAD
Final 3/3/2026 Corrections Issued JEFFREY MEAD
Service/Power Release 3/3/2026 Not Ready for Inspection JEFFREY MEAD
Final 3/11/2026 Not Ready for Inspection JEFFREY MEAD
Service/Power Release 3/11/2026 Not Ready for Inspection JEFFREY MEAD
Final 3/16/2026 Not Ready for Inspection JEFFREY MEAD
Service/Power Release 3/16/2026 Not Ready for Inspection JEFFREY MEAD
Final 3/26/2026 Partial Inspection JEFFREY MEAD
Service/Power Release 3/26/2026 Not Required JEFFREY MEAD
Final 4/3/2026 OK to Issue CofO RAUL BARAJAS
MERV13>=Final 4/3/2026 Approved RAUL BARAJAS