1853 N VISTA ST 90046
Certificate Information: 1853 N VISTA ST 90046
- Application / Permit
- 23010-30000-03239
- Plan Check / Job No.
- B23WL02027
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- BUILD NEW POOL TRELLIS ---3 OF 3---
- Permit Issued
- Issued on 11/16/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2023 | JOHNPAUL ISIP |
| Corrections Issued | 8/23/2023 | JOHNPAUL ISIP |
| Quality Review Completed | 8/28/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 8/31/2023 | APPLICANT |
| Applicant returned to address corrections | 10/19/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 11/16/2023 | JOHNPAUL ISIP |
| Issued | 11/16/2023 | APPLICANT |
| CofO in Progress | 10/10/2024 | BRIAN SULLIVAN |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
| CofO Issued | 11/1/2024 | DEROLD HAUFF |
| Permit Finaled | 11/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 10/27/2023 | YINGSHI HUANG |
Contact Information
| Contractor | 4 Diamond Contractors Inc; Lic. No.: 934766-B | 13983 BLOSSOM WAY EASTVALE, CA 92880 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
| Landscape Architect | Sosa,, Christopher Paul; Lic. No.: LA5442 | 8581 SANTA MONICA BLVD #255 WEST HOLLYWOOD, CA 90069 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/12/2024 | Approved | BRIAN SULLIVAN |
| Final | 9/12/2024 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 9/12/2024 | Approved | BRIAN SULLIVAN |
| Green Building Final | 9/12/2024 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 9/12/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 9/12/2024 | Not Required | BRIAN SULLIVAN |
| Smoke Detectors | 9/12/2024 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 9/12/2024 | Approved | BRIAN SULLIVAN |
| Final | 10/9/2024 | OK to Issue CofO | BRIAN SULLIVAN |