1184 N NORMANDIE AVE C-E 90029

Certificate Information: 1184 N NORMANDIE AVE C-E 90029

Application / Permit
23010-30000-03170
Plan Check / Job No.
B23WL01983
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX B WITH ATTACHED ADU AND ATTACHED 4 CARPORT IN BACK ----2 OF 2----
Permit Issued
Issued on 12/15/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2023 APPLICANT
Assigned to Plan Check Engineer 8/9/2023 KAVIAN REFAHI
Corrections Issued 8/13/2023 KAVIAN REFAHI
Quality Review Completed 8/15/2023 CHIHARU SUZUKI
Building Plans Picked Up 8/17/2023 APPLICANT
Disabled Access Plans Picked Up 9/14/2023 APPLICANT
Plan Check Approved 12/11/2023 KAVIAN REFAHI
Issued 12/15/2023 APPLICANT
CofO in Progress 1/27/2025 FREDDIE RIVERA
Permit Finaled 1/28/2025 DEROLD HAUFF
CofO Issued 1/28/2025 DEROLD HAUFF
Permit Finaled 1/28/2025 DEROLD HAUFF

Permit Application Clearance Information

SB8 RUD Cleared 8/23/2023 MARY ARCENA
Address approval Cleared 8/24/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/14/2023 WALLIE JONG
Sewer availability Cleared 9/14/2023 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 9/21/2023 FIPE LEILUA
Hydrant and Access approval Cleared 9/25/2023 KURT CORRAL
Low Impact Development (LID) Cleared 10/3/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/4/2023 CHRISTINA BRACO
Highway dedication Cleared 11/7/2023 TREVOR QUAN
DAS Clearance Cleared 11/28/2023 KAVIAN REFAHI

Contact Information

Contractor F S Z Bros General Contractors Inc; Lic. No.: 794097-B 9036 IMPERIAL HWY      DOWNEY, CA 90242

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/16/2024 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 1/18/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Approved FREDDIE RIVERA
PLUMBING-Rough 4/9/2024 Corrections Issued FREDDIE RIVERA
Deputy Wood Construction 4/10/2024 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 5/2/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/2/2024 Approved FREDDIE RIVERA
Green Building Rough 5/2/2024 Partial Inspection FREDDIE RIVERA
HVAC-Rough 5/2/2024 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 5/2/2024 Corrections Issued FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 5/2/2024 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 5/2/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 5/9/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/9/2024 Approved FREDDIE RIVERA
Green Building Rough 5/9/2024 Partial Inspection FREDDIE RIVERA
HVAC-Rough 5/9/2024 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 5/9/2024 Partial Approval FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 5/9/2024 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 5/9/2024 Approved FREDDIE RIVERA
HVAC-Rough 5/13/2024 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 5/16/2024 Approved FREDDIE RIVERA
Green Building Rough 5/16/2024 Approved FREDDIE RIVERA
Insulation 5/22/2024 Conditional Approval FREDDIE RIVERA
Drywall Nailing 6/3/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 6/3/2024 Partial Approval JOSH MEISTER
Interior/Exterior Lathing 6/21/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 6/24/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 9/4/2024 Corrections Issued FREDDIE RIVERA
Gas Test 9/4/2024 Approved FREDDIE RIVERA
HVAC-Final 9/4/2024 Approved FREDDIE RIVERA
PLUMBING-Final 9/4/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/27/2024 Partial Inspection FREDDIE RIVERA
Final 11/27/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 11/27/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Approved FREDDIE RIVERA
Service/Power Release 11/27/2024 Partial Inspection FREDDIE RIVERA
Smoke Detectors 11/27/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 12/24/2024 Partial Inspection FREDDIE RIVERA
Final 12/24/2024 Partial Inspection FREDDIE RIVERA
Gas Test 12/24/2024 Partial Inspection FREDDIE RIVERA
HVAC-Final 12/24/2024 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 12/24/2024 Partial Inspection FREDDIE RIVERA
Service/Power Release 12/24/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 1/6/2025 Approved FREDDIE RIVERA
Final 1/6/2025 OK to Issue CofO FREDDIE RIVERA
Gas Test 1/6/2025 Approved FREDDIE RIVERA
HVAC-Final 1/6/2025 Approved FREDDIE RIVERA
PLUMBING-Final 1/6/2025 Approved FREDDIE RIVERA
Service/Power Release 1/6/2025 Approved FREDDIE RIVERA