975-977 S BUNDY DR 90049
Certificate Information: 975-977 S BUNDY DR 90049
- Application / Permit
- 23010-30000-03078
- Plan Check / Job No.
- B23WL01923
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story house addition w/ attached 2-car garage and attached ADU PER LAMC 12.22 A.33(c) AND (e)*** 1 of 3 ***
- Permit Issued
- Issued on 9/20/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | YASHAR EMAMI |
| Corrections Issued | 8/8/2023 | YASHAR EMAMI |
| Quality Review Completed | 8/14/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 8/16/2023 | APPLICANT |
| Plan Check Approved | 9/18/2023 | YASHAR EMAMI |
| Issued | 9/20/2023 | APPLICANT |
| CofO in Progress | 12/23/2024 | KIRK SANDERS |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
| CofO Issued | 12/31/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/7/2023 | RUBEN VASQUEZ |
| ZI | Cleared | 8/7/2023 | RUBEN VASQUEZ |
| Address approval | Cleared | 8/8/2023 | DARIN LAM |
| Permit | Cleared | 8/8/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | DARIN LAM |
| Sewer availability | Cleared | 8/9/2023 | DARIN LAM |
| Specific Plan | Cleared | 8/11/2023 | ALESSANDRO MERCURI |
| Highway dedication | Cleared | 8/15/2023 | DINAH GARIN |
| Low Impact Development (LID) | Cleared | 8/30/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/3/2023 | AHMED AMARRAGY |
| Trees in Parkway | Cleared | 9/12/2023 | ADALBERTO VERA |
Contact Information
| Architect | Tucker,, Timothy Alan; Lic. No.: C19103 | 16934 EASTWOOD AVENUE TORRANCE, CA 90504 |
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | C R J Construction; Lic. No.: 1025947-B | 23679 CALABASAS RD #973 CALABASAS, CA 91302 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/15/2023 | Partial Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 11/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/29/2023 | Approved | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 12/1/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Partial Approval | ASHLEY THOMPSON |
| Deputy Wood Construction | 3/12/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/22/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 4/22/2024 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 4/26/2024 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 4/26/2024 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/1/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/1/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/10/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 5/10/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 5/14/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 5/20/2024 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 5/28/2024 | Corrections Issued | KIRK SANDERS |
| Insulation | 5/28/2024 | Approved | KIRK SANDERS |
| Drywall Nailing | 5/30/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 5/30/2024 | Approved | KIRK SANDERS |
| Shower Pan | 5/30/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 10/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 10/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 11/5/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 11/5/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 11/8/2024 | Corrections Issued | KIRK SANDERS |
| Gas Test | 11/8/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 11/8/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 11/8/2024 | Not Ready for Inspection | KIRK SANDERS |
| Service/Power Release | 11/8/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 11/13/2024 | Corrections Issued | KIRK SANDERS |
| Gas Test | 11/13/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 11/13/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 11/13/2024 | Not Ready for Inspection | KIRK SANDERS |
| Gas Test | 11/21/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 11/21/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 11/21/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 11/25/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 12/2/2024 | Approved | KIRK SANDERS |
| Final | 12/18/2024 | No Access for Inspection | KIRK SANDERS |
| Green Building Final | 12/18/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 12/18/2024 | No Access for Inspection | KIRK SANDERS |
| Final | 12/20/2024 | OK to Issue CofO | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 12/20/2024 | Approved | KIRK SANDERS |
| Smoke Detectors | 12/20/2024 | Approved | KIRK SANDERS |