15871 W MULHOLLAND DR 90049

Certificate Information: 15871 W MULHOLLAND DR 90049

Application / Permit
23010-30000-02731
Plan Check / Job No.
B23WL01698
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(18) School Building
Work Description
New 2-story over 1-level basement Curtis private schoool building
Permit Issued
Issued on 7/10/2024
Issuing Office
Current Status
CofO Issued on 11/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2023 APPLICANT
Assigned to Plan Check Engineer 7/7/2023 REZA HAGHIGHAT
Corrections Issued 8/1/2023 REZA HAGHIGHAT
Quality Review Completed 8/15/2023 CHIHARU SUZUKI
Building Plans Picked Up 8/16/2023 APPLICANT
Green Plans Picked Up 8/17/2023 APPLICANT
Applicant returned to address corrections 11/22/2023 REZA HAGHIGHAT
Applicant returned to address corrections 2/29/2024 REZA HAGHIGHAT
Applicant returned to address corrections 3/7/2024 REZA HAGHIGHAT
Plan Check Approved 7/10/2024 REZA HAGHIGHAT
Issued 7/10/2024 APPLICANT
TCO Issued (Expire Date: 04-07-2026) 10/9/2025 JEFFREY DURAN
CofO in Progress 11/12/2025 DEANDRE HOFFMAN
Permit Finaled 11/14/2025 RICKEY JACKSON
CofO Issued 11/14/2025 RICKEY JACKSON
Permit Finaled 11/14/2025 RICKEY JACKSON

Permit Application Clearance Information

CPC Cleared 9/20/2023 RYAN LY
CPC Cleared 9/20/2023 RYAN LY
ZA Case Cleared 9/20/2023 RYAN LY
ZA Case Cleared 9/20/2023 RYAN LY
ZA Case Cleared 9/20/2023 RYAN LY
ZA Case Cleared 9/20/2023 RYAN LY
Address approval Cleared 12/12/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/12/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/12/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/12/2023 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/12/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/14/2023 CARLOS AGUILERA
Distance to fire station Cleared 2/5/2024 KURT CORRAL
Hydrant and Access approval Cleared 2/5/2024 KURT CORRAL
Green Code Cleared 2/27/2024 AARON COSTA
Fire Marshal Fire Life Safety Cleared 4/11/2024 FIRE DEPARTMENT
DAS Clearance Cleared 4/23/2024 SHINE LIN
Sewer availability Cleared 5/30/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 6/8/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 6/9/2024 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 6/25/2024 CARLOS AGUILERA
CPC Cleared 7/2/2024 YINGSHI HUANG
Miscellaneous Cleared 7/2/2024 YINGSHI HUANG
Site Plan review Cleared 7/2/2024 YINGSHI HUANG
Specific Plan Cleared 7/2/2024 YINGSHI HUANG
Specific Plan Cleared 7/2/2024 YINGSHI HUANG
ZA Case Cleared 7/2/2024 YINGSHI HUANG
Excavation more than 5-ft deep Cleared 7/10/2024 CALOSHA APPROVED
GPI Written Notices Cleared 7/10/2024 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 7/10/2024 REZA HAGHIGHAT

Contact Information

Architect Pica,, V Joseph; Lic. No.: C15657 1038 SOUTH ALFRED STREET      LOS ANGELES, CA 90035
Contractor Matt Construction Corporation; Lic. No.: 631020-B 9814 NORWALK BLVD #100      SANTA FE SPRINGS, CA 90670
Engineer Ganju,, Sharad; Lic. No.: C85128 6050 CADILLAC AVE APT 205      LOS ANGELES, CA 90034
Engineer Harris,, William Donald; Lic. No.: S5121 26344 DUNWOOD RD      ROLLING HILLS ESTATES, CA 90274
Engineer Johnson,, David D.B.; Lic. No.: S3032 7724 W 83RD ST      PLAYA DEL REY, CA 90293
Engineer Marcus,, Matthew Werner; Lic. No.: GE3156 2154 TORRANCE BLVD      TORRANCE, CA 90501
Engineer Stewart,, Joseph E; Lic. No.: S3065 4117 MEADOW LARK DR      CALABASAS, CA 91302

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/14/2024 Partial Inspection GREGORY POMISH
Piling/Pier/Caisson 8/23/2024 Partial Inspection ROBERT DAVIS
Pre-Inspection 8/23/2024 Partial Inspection ROBERT DAVIS
Green Building Rough 8/26/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 8/26/2024 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 8/26/2024 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 8/29/2024 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 9/5/2024 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 9/5/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 9/5/2024 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 9/5/2024 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Verify Sprinkler Sign Off 9/5/2024 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/6/2024 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/13/2024 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/25/2024 Partial Approval ROBERT DAVIS
Deputy Shotcrete 10/24/2024 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 10/24/2024 Not Ready for Inspection GREGORY POMISH
Green Building Rough 10/24/2024 Partial Inspection GREGORY POMISH
Piling/Pier/Caisson 10/24/2024 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 10/24/2024 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 10/24/2024 Not Ready for Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 10/25/2024 Partial Approval GREGORY POMISH
Piling/Pier/Caisson 10/25/2024 Partial Approval GREGORY POMISH
Deputy Shotcrete 10/31/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 10/31/2024 Partial Approval ROBERT DAVIS
Green Building Rough 10/31/2024 Not Ready for Inspection ROBERT DAVIS
Piling/Pier/Caisson 10/31/2024 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 10/31/2024 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 10/31/2024 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 11/1/2024 Not Ready for Inspection ROBERT DAVIS
Masonry Wall/Backfill 11/13/2024 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 11/15/2024 Partial Approval ROBERT DAVIS
Reinforced Masonry Frame 11/15/2024 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 11/18/2024 Partial Inspection JOHN KITCKO
Masonry Wall/Backfill 11/18/2024 Partial Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 12/23/2024 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 1/6/2025 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 1/24/2025 Partial Approval ROBERT DAVIS
Deputy Fireproofing 1/31/2025 Conditional Approval ROBERT DAVIS
Green Building Rough 2/18/2025 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 2/18/2025 Not Ready for Inspection ROBERT DAVIS
Structural Steel Frame 2/18/2025 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 2/18/2025 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 2/21/2025 Not Ready for Inspection GREGORY POMISH
Light Gage Steel Frame 2/24/2025 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 2/26/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 3/3/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 3/28/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 3/28/2025 Partial Approval ROBERT DAVIS
Insulation 3/28/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 3/28/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 4/2/2025 Partial Approval ROBERT DAVIS
Green Building Rough 4/2/2025 Not Ready for Inspection ROBERT DAVIS
Insulation 4/2/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 4/2/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 4/10/2025 Conditional Approval ROBERT DAVIS
Green Building Rough 4/10/2025 Not Ready for Inspection ROBERT DAVIS
Insulation 4/10/2025 Partial Approval ROBERT DAVIS
Masonry Wall/Backfill 4/10/2025 Not Ready for Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Not Ready for Inspection ROBERT DAVIS
Structural Steel Frame 4/15/2025 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 4/17/2025 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 4/23/2025 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 4/23/2025 Partial Approval GREGORY POMISH
Green Building Rough 4/23/2025 Partial Inspection GREGORY POMISH
Insulation 4/23/2025 Not Ready for Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 4/25/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 4/30/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 5/6/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 5/7/2025 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 5/7/2025 Not Ready for Inspection ROBERT DAVIS
Insulation 5/7/2025 Not Ready for Inspection ROBERT DAVIS
Interior/Exterior Lathing 5/7/2025 Conditional Approval ROBERT DAVIS
Insulation 5/8/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 5/8/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 5/13/2025 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 5/13/2025 Approved ROBERT DAVIS
Interior/Exterior Lathing 5/13/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 5/14/2025 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 5/19/2025 Partial Inspection ROBERT DAVIS
Insulation 5/19/2025 Partial Approval ROBERT DAVIS
Special/Order Compliance 5/22/2025 Partial Inspection ROBERT DAVIS
Drywall Nailing 5/27/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 5/27/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 5/28/2025 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 5/28/2025 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 6/3/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 6/3/2025 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 6/4/2025 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 6/5/2025 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 6/6/2025 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 6/9/2025 Partial Inspection BRIAN KELLY
Insulation 6/9/2025 Partial Inspection BRIAN KELLY
Insulation 6/10/2025 Partial Inspection DANIEL VARNUM
Drywall Nailing 6/12/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 6/12/2025 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 6/17/2025 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 6/18/2025 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 6/18/2025 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/25/2025 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 7/7/2025 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 7/10/2025 Partial Approval ROBERT DAVIS
Special/Order Compliance 7/10/2025 Partial Inspection ROBERT DAVIS
T-Bar Ceiling 7/11/2025 Not Ready for Inspection ROBERT DAVIS
T-Bar Ceiling 7/24/2025 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 7/29/2025 No Access for Inspection ROBERT DAVIS
T-Bar Ceiling 7/31/2025 Partial Approval ROBERT DAVIS
T-Bar Ceiling 8/8/2025 Approved ROBERT DAVIS
Posting Pre-Inspection 8/18/2025 Partial Inspection ROBERT DAVIS
Special/Order Compliance 8/18/2025 Corrections Issued ROBERT DAVIS
Drywall Nailing 9/22/2025 Approved ROBERT DAVIS
Final 9/22/2025 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 9/22/2025 Approved ROBERT DAVIS
Green Building Final 9/22/2025 Approved ROBERT DAVIS
Reinforced Concrete Frame 9/22/2025 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV No Gas ROBERT DAVIS
Smoke Detectors 9/22/2025 Not Ready for Inspection ROBERT DAVIS
Structural Steel Frame 9/22/2025 Approved ROBERT DAVIS
Verify Sprinkler Sign Off 9/22/2025 Approved ROBERT DAVIS
Wood Frame 9/22/2025 Approved ROBERT DAVIS
Deputy Shotcrete 11/12/2025 Approved DEANDRE HOFFMAN
Final 11/12/2025 OK to Issue CofO DEANDRE HOFFMAN
Smoke Detectors 11/12/2025 Approved DEANDRE HOFFMAN