417 N KENMORE AVE 1-3 90004

Certificate Information: 417 N KENMORE AVE 1-3 90004

Application / Permit
23010-30000-02575
Plan Check / Job No.
B23WL01622
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX WITH ROOF DECK AND AN ATTACHED ADU PER LAMC 12.22 A.33(c) and (e). (rear building) ----2 OF 2----
Permit Issued
Issued on 1/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2023 APPLICANT
Assigned to Plan Check Engineer 6/21/2023 KAVIAN REFAHI
Corrections Issued 6/24/2023 KAVIAN REFAHI
Quality Review Completed 6/28/2023 CHIHARU SUZUKI
Building Plans Picked Up 6/29/2023 APPLICANT
Disabled Access Plans Picked Up 7/20/2023 APPLICANT
Applicant returned to address corrections 12/18/2023 KAVIAN REFAHI
Plan Check Approved 12/19/2023 KAVIAN REFAHI
Issued 1/19/2024 APPLICANT
CofO in Progress 5/23/2025 FREDDIE RIVERA
Permit Finaled 5/25/2025 DEROLD HAUFF
CofO Issued 5/25/2025 DEROLD HAUFF
Permit Finaled 5/25/2025 DEROLD HAUFF

Permit Application Clearance Information

SB8 RUD Cleared 6/22/2023 MARY ARCENA
Address approval Cleared 7/5/2023 JEANIE LAM
Highway dedication Cleared 7/5/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/6/2023 JEANIE LAM
Sewer availability Cleared 7/6/2023 JEANIE LAM
Frnt yard landscape/Water mgmt Cleared 7/17/2023 ASHLEY RODARTE
Low Impact Development (LID) Cleared 7/18/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 7/19/2023 JEANIE LAM
Hydrant and Access approval Cleared 8/8/2023 KURT CORRAL
Flood clearance Cleared 9/8/2023 ABDULRAHMAN ALABTAH
DAS Clearance Cleared 9/21/2023 KAVIAN REFAHI
Construction within easement Cleared 11/16/2023 RIDWAN HARDY
Building over 36-ft Cleared 12/19/2023 CALOSHA APPROVED

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/12/2024 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 3/26/2024 Partial Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 3/26/2024 Approved JOSEPH MCGARRY
FLOOD-Elevation Certificate 3/26/2024 Approved JOSEPH MCGARRY
Deputy Wood Construction 4/19/2024 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/19/2024 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 4/25/2024 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Partial Approval SCOTT FINNILA
Deputy Wood Construction 5/10/2024 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 6/3/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Conditional Approval FREDDIE RIVERA
HVAC-Rough 6/3/2024 Approved FREDDIE RIVERA
PLUMBING-Rough 6/3/2024 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 6/5/2024 Corrections Issued FREDDIE RIVERA
Deputy Wood Construction 6/28/2024 Conditional Approval FREDDIE RIVERA
Shower Pan 7/9/2024 Approved JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Approved FREDDIE RIVERA
Wood Frame 7/10/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 7/12/2024 Corrections Issued FREDDIE RIVERA
FLOOD-Proofing Certificate 7/12/2024 Approved FREDDIE RIVERA
Green Building Rough 7/12/2024 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 7/12/2024 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 7/16/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 7/17/2024 Approved BRENDAN MORELLI
Insulation 7/22/2024 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 7/25/2024 Approved JUSTIN HAWLEY
Insulation 7/29/2024 Approved ANTHONY RAMOS
Drywall Nailing 8/8/2024 Approved FREDDIE RIVERA
HVAC-Final 1/21/2025 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 1/24/2025 Corrections Issued FREDDIE RIVERA
HVAC-Final 1/24/2025 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Final 1/28/2025 Approved FREDDIE RIVERA
HVAC-Final 1/30/2025 Approved FREDDIE RIVERA
PLUMBING-Final 1/30/2025 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 2/5/2025 Approved FREDDIE RIVERA
Final 4/9/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 4/9/2025 Approved FREDDIE RIVERA
Green Building Final 4/9/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Approved FREDDIE RIVERA
Service/Power Release 4/9/2025 Approved FREDDIE RIVERA
Smoke Detectors 4/9/2025 Approved FREDDIE RIVERA
Final 4/22/2025 Corrections Issued FREDDIE RIVERA
Final 5/23/2025 OK to Issue CofO FREDDIE RIVERA