646-646 1/2 N BOYLE AVE 90033
Certificate Information: 646-646 1/2 N BOYLE AVE 90033
- Application / Permit
- 23010-30000-02573
- Plan Check / Job No.
- B23WL01620
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX W/ GARAGE (REAR) ----2 OF 3----
- Permit Issued
- Issued on 8/18/2023
- Issuing Office
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2023 | KAVIAN REFAHI |
| Corrections Issued | 6/25/2023 | KAVIAN REFAHI |
| Quality Review Completed | 6/28/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/29/2023 | APPLICANT |
| Plan Check Approved | 8/16/2023 | KAVIAN REFAHI |
| Issued | 8/18/2023 | APPLICANT |
| CofO in Progress | 4/28/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2023 | CHRISTINA BRACO |
| Highway dedication | Cleared | 7/7/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 7/7/2023 | CHRISTINA BRACO |
| Frnt yard landscape/Water mgmt | Cleared | 7/12/2023 | ALEX VELA |
| SB8 RUD | Cleared | 7/12/2023 | JAMES MCCARTHY |
| ZA Case | Cleared | 7/12/2023 | ALEX VELA |
| ZI | Cleared | 7/12/2023 | ALEX VELA |
| Low Impact Development (LID) | Cleared | 7/13/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/13/2023 | CHRISTINA BRACO |
| Hydrant and Access approval | Cleared | 8/7/2023 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 8/16/2023 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 8/16/2023 | KAVIAN REFAHI |
Contact Information
| Architect | Tucker,, Timothy Alan; Lic. No.: C19103 | 16934 EASTWOOD AVENUE TORRANCE, CA 90504 |
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Lee,, Allen C; Lic. No.: GE2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/5/2023 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 10/13/2023 | Partial Approval | OSVALDO PARAMO |
| METHANE-Barrier | 10/13/2023 | Approved | OSVALDO PARAMO |
| METHANE-Subgrade | 10/13/2023 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/22/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/10/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Rough | 4/10/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 4/10/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 4/16/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/17/2024 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 4/19/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 4/22/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/7/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 5/7/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/9/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 5/9/2024 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 5/9/2024 | Approved | OSVALDO PARAMO |
| METHANE-Rough | 5/9/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 5/9/2024 | Approved | OSVALDO PARAMO |
| Insulation | 5/20/2024 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 6/20/2024 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 7/10/2024 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 8/26/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 12/13/2024 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Final | 4/24/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/24/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Final | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/25/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/28/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |