4243 S GRAND VIEW BLVD 90066

Certificate Information: 4243 S GRAND VIEW BLVD 90066

Application / Permit
23010-30000-02418
Plan Check / Job No.
B23WL01518
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New det. 1-story ADU at rear of the lot per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 10/23/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/15/2023 REZA HAGHIGHAT
Corrections Issued 6/18/2023 REZA HAGHIGHAT
Quality Review Completed 6/26/2023 KAVIAN REFAHI
Building Plans Picked Up 6/29/2023 APPLICANT
Plan Check Approved 10/23/2023 REZA HAGHIGHAT
Issued 10/23/2023 APPLICANT
CofO in Progress 4/22/2025 MICHAEL ALLEN
CofO Issued 4/22/2025 RICHARD STEINBACH
Permit Finaled 4/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/10/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 7/10/2023 JASON NG
Sewer availability Cleared 7/10/2023 JASON NG
Specific Plan Cleared 8/17/2023 JOSHUA JONES
Hydrant and Access approval Cleared 8/30/2023 KURT CORRAL
Low Impact Development (LID) Cleared 10/3/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 10/4/2023 BRENDEN HAWK
Construction near power lines Cleared 10/10/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/19/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 12/19/2023 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/25/2024 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 1/25/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Approved TEMISTOCLES CAAL
Underground Mechanical 3/26/2024 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 5/29/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/29/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 6/5/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Approved JESUS RODRIGUEZ
Green Building Rough 6/5/2024 Not Ready for Inspection JESUS RODRIGUEZ
Verify Sprinkler Sign Off 6/5/2024 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 7/22/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 8/6/2024 Approved JESUS RODRIGUEZ
Green Building Rough 8/6/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/6/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 8/6/2024 Approved JESUS RODRIGUEZ
Shower Pan 8/20/2024 Approved JESUS RODRIGUEZ
Insulation 8/23/2024 Approved JESUS PINEDA
Drywall Nailing 8/28/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 9/16/2024 Approved JESUS PINEDA
ELECTRICAL-Final 3/3/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 3/3/2025 Approved JESUS PINEDA
ELECTRICAL-Final 3/19/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 3/19/2025 Conditional Approval MICHAEL ALLEN
ELECTRICAL-Final 3/27/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 3/27/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 4/2/2025 Approved MICHAEL ALLEN
Service/Power Release 4/2/2025 Conditional Approval MICHAEL ALLEN
Final 4/4/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 4/4/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 4/4/2025 Approved MICHAEL ALLEN
Final 4/21/2025 OK to Issue CofO MICHAEL ALLEN
Service/Power Release 4/21/2025 Approved MICHAEL ALLEN