4243 S GRAND VIEW BLVD 90066
Certificate Information: 4243 S GRAND VIEW BLVD 90066
- Application / Permit
- 23010-30000-02418
- Plan Check / Job No.
- B23WL01518
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New det. 1-story ADU at rear of the lot per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 10/23/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2023 | REZA HAGHIGHAT |
| Corrections Issued | 6/18/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 6/26/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 6/29/2023 | APPLICANT |
| Plan Check Approved | 10/23/2023 | REZA HAGHIGHAT |
| Issued | 10/23/2023 | APPLICANT |
| CofO in Progress | 4/22/2025 | MICHAEL ALLEN |
| CofO Issued | 4/22/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/22/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/10/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2023 | JASON NG |
| Sewer availability | Cleared | 7/10/2023 | JASON NG |
| Specific Plan | Cleared | 8/17/2023 | JOSHUA JONES |
| Hydrant and Access approval | Cleared | 8/30/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 10/3/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 10/4/2023 | BRENDEN HAWK |
| Construction near power lines | Cleared | 10/10/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 12/19/2023 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 1/25/2024 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/25/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 3/26/2024 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 5/29/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/29/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/5/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/5/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/5/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/22/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/6/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/6/2024 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/6/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 8/20/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/23/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 8/28/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/16/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 3/3/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 3/3/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 3/19/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 3/19/2025 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Final | 3/27/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 3/27/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 4/2/2025 | Approved | MICHAEL ALLEN |
| Service/Power Release | 4/2/2025 | Conditional Approval | MICHAEL ALLEN |
| Final | 4/4/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 4/4/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 4/4/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 4/4/2025 | Approved | MICHAEL ALLEN |
| Final | 4/21/2025 | OK to Issue CofO | MICHAEL ALLEN |
| Service/Power Release | 4/21/2025 | Approved | MICHAEL ALLEN |