2 N OAKMONT DR 90049

Certificate Information: 2 N OAKMONT DR 90049

Application / Permit
23010-30000-02258
Plan Check / Job No.
B23WL01428
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
NEW MECHANICAL ENCLOSURE BUILDING WITH STEEL BEAMS AND CMU WALLS.
Permit Issued
Issued on 9/22/2023
Issuing Office
Current Status
CofO Issued on 9/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2023 APPLICANT
Assigned to Plan Check Engineer 5/31/2023 SERGIO SILVA
Corrections Issued 6/7/2023 SERGIO SILVA
Quality Review Completed 6/8/2023 KAVIAN REFAHI
Building Plans Picked Up 6/9/2023 APPLICANT
Plan Check Approved 9/22/2023 SERGIO SILVA
Issued 9/22/2023 APPLICANT
CofO in Progress 7/30/2024 KEVIN SARGSYAN
Permit Finaled 9/26/2024 RICHARD STEINBACH
CofO Issued 9/26/2024 RICHARD STEINBACH
Permit Finaled 9/26/2024 RICHARD STEINBACH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/12/2023 JASON NG
BHO/Hillside ordinance Cleared 9/12/2023 JASON NG
BHO/Hillside ordinance Cleared 9/12/2023 JASON NG
CPC Cleared 9/12/2023 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 9/12/2023 JASON NG
Low Impact Development Cleared 9/12/2023 MARTIN FRAGOSO
Sewer availability Cleared 9/12/2023 JASON NG
Roof/Waste drainage to street Cleared 9/13/2023 JASON NG
Grading Pre-Inspection Cleared 9/19/2023 VASIL MIHALEV
Hydrant and Access approval Cleared 9/21/2023 GILBERT URREA

Contact Information

Contractor Holz Richard Inc; Lic. No.: 294504-B 520 S SEPULVEDA BLVD #407      WLOS ANGELES, CA 90049
Engineer Kwan,, Denny Chi-Ho; Lic. No.: S4887 5638 NEWFIELDS LN      DUBLIN, CA 94568

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/24/2024 Approved KEVIN SARGSYAN
Final 7/24/2024 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 7/24/2024 Approved KEVIN SARGSYAN
Green Building Final 7/24/2024 Approved KEVIN SARGSYAN
Green Building Rough 7/24/2024 Approved KEVIN SARGSYAN
Reinforced Masonry Frame 7/24/2024 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/24/2024 SGSOV Approved KEVIN SARGSYAN
Drywall Nailing 7/30/2024 Approved KEVIN SARGSYAN
Final 7/30/2024 OK to Issue CofO KEVIN SARGSYAN
Service/Power Release 7/30/2024 Approved KEVIN SARGSYAN
Smoke Detectors 7/30/2024 Approved KEVIN SARGSYAN