635 N MARIPOSA AVE 90004

Certificate Information: 635 N MARIPOSA AVE 90004

Application / Permit
23010-30000-02199
Plan Check / Job No.
B23WL01400
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached accessory dwelling unit of 336 SF per LAMC 12.22 A.33 (c)-(d). All work per architect.
Permit Issued
Issued on 4/9/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 RICHARD GARCIA
Corrections Issued 6/1/2023 RICHARD GARCIA
Building Plans Picked Up 6/6/2023 APPLICANT
Applicant returned to address corrections 9/8/2023 VICTOR CHEN
Plan Check Approved 11/9/2023 JOSEPH RAFOLS
Issued 4/9/2024 APPLICANT
CofO in Progress 1/23/2026 FREDDIE RIVERA
Permit Finaled 1/26/2026 DEROLD HAUFF
CofO Issued 1/26/2026 DEROLD HAUFF
Permit Finaled 1/26/2026 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 6/30/2023 MAXFIELD VERMY
ZI Cleared 6/30/2023 MAXFIELD VERMY
Address approval Cleared 7/5/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/6/2023 JESSICA OPINION
Sewer availability Cleared 7/6/2023 JESSICA OPINION
Low Impact Development (LID) Cleared 8/29/2023 TRISH PARAS
Roof/Waste drainage to street Cleared 9/6/2023 AHMED AMARRAGY

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Bluestone Contracting Inc; Lic. No.: 788295-B 1101 16TH STREET      SANTA MONICA, CA 90403

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2024 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 4/16/2024 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/10/2024 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 10/11/2024 Approved FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 10/11/2024 Corrections Issued FREDDIE RIVERA
Pre-Inspection 3/19/2025 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 4/10/2025 Conditional Approval FREDDIE RIVERA
Green Building Rough 4/10/2025 Approved FREDDIE RIVERA
MERV13>=Rough 4/10/2025 Approved FREDDIE RIVERA
Insulation 4/22/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/22/2025 Partial Approval FREDDIE RIVERA
Drywall Nailing 4/24/2025 Approved ALEX COLIN
BUILDING-Rough-Frame 8/8/2025 Approved ALIZAH MAYAGOITIA
Final 8/8/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/8/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 8/8/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Final 8/8/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 8/8/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 8/8/2025 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 8/8/2025 Approved ALIZAH MAYAGOITIA
Final 8/27/2025 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Approved FREDDIE RIVERA
Service/Power Release 8/27/2025 Approved FREDDIE RIVERA
Final 12/16/2025 Partial Inspection FREDDIE RIVERA
Final 12/17/2025 Partial Inspection FREDDIE RIVERA
Final 1/22/2026 OK to Issue CofO FREDDIE RIVERA