1642 N GARDNER ST 90046
Certificate Information: 1642 N GARDNER ST 90046
- Application / Permit
- 23010-30000-02088
- Plan Check / Job No.
- B23WL01305
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2 story accessory building. 1st floor rec-room with ADU on 2nd floor per ordinance.
- Permit Issued
- Issued on 3/24/2025
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | KAVIAN REFAHI |
| Corrections Issued | 5/26/2023 | KAVIAN REFAHI |
| Quality Review Completed | 5/30/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/1/2023 | APPLICANT |
| Applicant returned to address corrections | 7/6/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/24/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/7/2023 | KAVIAN REFAHI |
| Plan Check Approved | 11/15/2023 | KAVIAN REFAHI |
| Issued | 3/24/2025 | APPLICANT |
| CofO in Progress | 3/31/2026 | ROY SPAULDING |
| Permit Finaled | 4/3/2026 | DEROLD HAUFF |
| CofO Issued | 4/3/2026 | DEROLD HAUFF |
| Permit Finaled | 4/3/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2023 | JEANIE LAM |
| Sewer availability | Cleared | 7/13/2023 | JEANIE LAM |
| Low Impact Development (LID) | Cleared | 8/2/2023 | ERNEST TSE |
| HPOZ | Cleared | 8/9/2023 | ERIK VAN BREENE |
| Construction near power lines | Cleared | 10/12/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 10/18/2023 | ARNULFO CHAMU |
| Miscellaneous | Cleared | 10/19/2023 | JOE TAM |
| Miscellaneous | Cleared | 10/19/2023 | JOE TAM |
| Miscellaneous | Cleared | 10/19/2023 | JOE TAM |
| Hydrant and Access approval | Cleared | 11/13/2023 | JOHN CONNEALLY |
Contact Information
| Architect | Griffin,, Margaret P; Lic. No.: C26524 | 1357 SUNSET AVENUE SANTA MONICA, CA 90405 |
| Contractor | Espana Builders; Lic. No.: 1002026-B | 20929 SILVERGATE WAY SANTA CLARITA, CA 91321 |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/1/2025 | Partial Inspection | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 5/6/2025 | Corrections Issued | ROY SPAULDING |
| Footing/Foundation/Slab | 5/6/2025 | Not Ready for Inspection | ROY SPAULDING |
| Grounding or Bonding | 5/6/2025 | Approved | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 5/16/2025 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 5/16/2025 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Partial Approval | ROY SPAULDING |
| Pre-Inspection | 6/25/2025 | Partial Inspection | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 7/23/2025 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 8/12/2025 | Approved | ROY SPAULDING |
| Gas Test | 8/12/2025 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 8/12/2025 | Approved | ROY SPAULDING |
| Sewer | 8/12/2025 | Approved | ROY SPAULDING |
| Underground Mechanical | 8/12/2025 | Approved | ROY SPAULDING |
| Special/Order Compliance | 8/14/2025 | Partial Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 9/3/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/5/2025 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 9/5/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 9/5/2025 | Approved | BRIAN SULLIVAN |
| Wood Frame | 9/5/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/24/2025 | Approved | ROY SPAULDING |
| Green Building Rough | 9/24/2025 | Approved | ROY SPAULDING |
| Wood Frame | 9/24/2025 | Approved | ROY SPAULDING |
| Insulation | 9/30/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 9/30/2025 | Approved | ROY SPAULDING |
| Drywall Nailing | 10/6/2025 | Approved | ROY SPAULDING |
| Shower Pan | 10/14/2025 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 2/6/2026 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Final | 2/6/2026 | Not Ready for Inspection | ROY SPAULDING |
| Service/Power Release | 2/6/2026 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 2/6/2026 | Not Ready for Inspection | ROY SPAULDING |
| Final | 3/12/2026 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 3/12/2026 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 3/12/2026 | Corrections Issued | ROY SPAULDING |
| Smoke Detectors | 3/12/2026 | Approved | ROY SPAULDING |
| Final | 3/25/2026 | OK to Issue CofO | ROY SPAULDING |
| Service/Power Release | 3/25/2026 | Approved | ROY SPAULDING |