2637 S GARTH AVE A - B 90034
Certificate Information: 2637 S GARTH AVE A - B 90034
- Application / Permit
- 23010-30000-02061
- Plan Check / Job No.
- B23WL01293
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-story duplex (A) at front of the lot
- Permit Issued
- Issued on 9/6/2023
- Issuing Office
- Current Status
- CofO Issued on 8/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2023 | REZA HAGHIGHAT |
| Corrections Issued | 5/20/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 5/26/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/21/2023 | APPLICANT |
| Plan Check Approved | 8/24/2023 | REZA HAGHIGHAT |
| Issued | 9/6/2023 | APPLICANT |
| CofO in Progress | 8/13/2025 | EVAN COOPER |
| Permit Finaled | 8/22/2025 | RICHARD STEINBACH |
| CofO Issued | 8/22/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/22/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| SB8 RUD | Cleared | 5/24/2023 | PATRICIA ALFARO |
| "Q" conditions | Cleared | 6/2/2023 | NATHAN ROMINE |
| Prkng lot landscape/Water mgmt | Cleared | 6/2/2023 | NATHAN ROMINE |
| Address approval | Cleared | 6/5/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2023 | WALLIE JONG |
| Sewer availability | Cleared | 6/6/2023 | WALLIE JONG |
| Opn space landscape/Water mgmt | Cleared | 6/8/2023 | NATHAN ROMINE |
| Highway dedication | Cleared | 6/13/2023 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 6/20/2023 | MAYELA VILLA |
| Hydrant and Access approval | Cleared | 6/22/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 8/16/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 8/16/2023 | ABEL CASILLAS |
Contact Information
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 15831 SAN JOSE AVE LA PUENTE, CA 91744 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/15/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 9/20/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/20/2023 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 9/21/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/21/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/17/2023 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/5/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/5/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Wood Construction | 6/25/2024 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 6/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 6/26/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 6/26/2024 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 7/16/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 7/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 7/16/2024 | Approved | MEL KHACHATOURIAN |
| MERV13>=Rough | 7/16/2024 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 7/16/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 7/25/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 7/25/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 7/30/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 7/30/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 7/30/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 8/2/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 8/9/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 8/16/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/20/2024 | Not Ready for Inspection | SEAN HAUPT |
| Sewer | 1/28/2025 | Approved | SEAN HAUPT |
| Underground Mechanical | 1/28/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 7/23/2025 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 7/23/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 7/23/2025 | Corrections Issued | EVAN COOPER |
| Service/Power Release | 7/23/2025 | Not Ready for Inspection | EVAN COOPER |
| Final | 8/8/2025 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 8/8/2025 | Approved | EVAN COOPER |
| MERV13>=Final | 8/8/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 8/8/2025 | Approved | EVAN COOPER |
| Smoke Detectors | 8/8/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/13/2025 | Approved | EVAN COOPER |
| Final | 8/13/2025 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 8/13/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/13/2025 | Approved | EVAN COOPER |
| Service/Power Release | 8/13/2025 | Approved | EVAN COOPER |