2637 S GARTH AVE A - B 90034

Certificate Information: 2637 S GARTH AVE A - B 90034

Application / Permit
23010-30000-02061
Plan Check / Job No.
B23WL01293
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3-story duplex (A) at front of the lot
Permit Issued
Issued on 9/6/2023
Issuing Office
Current Status
CofO Issued on 8/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2023 APPLICANT
Assigned to Plan Check Engineer 5/17/2023 REZA HAGHIGHAT
Corrections Issued 5/20/2023 REZA HAGHIGHAT
Quality Review Completed 5/26/2023 CHIHARU SUZUKI
Building Plans Picked Up 6/21/2023 APPLICANT
Plan Check Approved 8/24/2023 REZA HAGHIGHAT
Issued 9/6/2023 APPLICANT
CofO in Progress 8/13/2025 EVAN COOPER
Permit Finaled 8/22/2025 RICHARD STEINBACH
CofO Issued 8/22/2025 RICHARD STEINBACH
Permit Finaled 8/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

SB8 RUD Cleared 5/24/2023 PATRICIA ALFARO
"Q" conditions Cleared 6/2/2023 NATHAN ROMINE
Prkng lot landscape/Water mgmt Cleared 6/2/2023 NATHAN ROMINE
Address approval Cleared 6/5/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/5/2023 WALLIE JONG
Sewer availability Cleared 6/6/2023 WALLIE JONG
Opn space landscape/Water mgmt Cleared 6/8/2023 NATHAN ROMINE
Highway dedication Cleared 6/13/2023 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 6/20/2023 MAYELA VILLA
Hydrant and Access approval Cleared 6/22/2023 KURT CORRAL
Low Impact Development Cleared 8/16/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 8/16/2023 ABEL CASILLAS

Contact Information

Contractor C S W F Construction Inc; Lic. No.: 1021458-B 15831 SAN JOSE AVE      LA PUENTE, CA 91744
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/15/2023 Corrections Issued MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 9/20/2023 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 9/20/2023 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 9/21/2023 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 9/21/2023 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 10/17/2023 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 6/5/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 6/5/2024 Not Ready for Inspection MEL KHACHATOURIAN
Deputy Wood Construction 6/25/2024 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 6/26/2024 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 6/26/2024 Approved ASHLEY THOMPSON
PLUMBING-Rough 6/26/2024 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/16/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 7/16/2024 Partial Approval MEL KHACHATOURIAN
Green Building Rough 7/16/2024 Approved MEL KHACHATOURIAN
MERV13>=Rough 7/16/2024 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 7/16/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/25/2024 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 7/25/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/30/2024 Corrections Issued MEL KHACHATOURIAN
Interior/Exterior Lathing 7/30/2024 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 7/30/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 8/2/2024 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 8/2/2024 Approved MEL KHACHATOURIAN
Insulation 8/9/2024 Partial Approval MEL KHACHATOURIAN
Drywall Nailing 8/16/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 8/16/2024 Partial Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 8/20/2024 Not Ready for Inspection SEAN HAUPT
Sewer 1/28/2025 Approved SEAN HAUPT
Underground Mechanical 1/28/2025 Approved SEAN HAUPT
ELECTRICAL-Final 7/23/2025 Corrections Issued EVAN COOPER
HVAC-Final 7/23/2025 Corrections Issued EVAN COOPER
PLUMBING-Final 7/23/2025 Corrections Issued EVAN COOPER
Service/Power Release 7/23/2025 Not Ready for Inspection EVAN COOPER
Final 8/8/2025 Not Ready for Inspection EVAN COOPER
Green Building Final 8/8/2025 Approved EVAN COOPER
MERV13>=Final 8/8/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Approved EVAN COOPER
Service/Power Release 8/8/2025 Approved EVAN COOPER
Smoke Detectors 8/8/2025 Approved EVAN COOPER
ELECTRICAL-Final 8/13/2025 Approved EVAN COOPER
Final 8/13/2025 OK to Issue CofO EVAN COOPER
HVAC-Final 8/13/2025 Approved EVAN COOPER
PLUMBING-Final 8/13/2025 Approved EVAN COOPER
Service/Power Release 8/13/2025 Approved EVAN COOPER