657 1/2-659 1/2 E VERNON AVE 90011
Certificate Information: 657 1/2-659 1/2 E VERNON AVE 90011
- Application / Permit
- 23010-30000-01949
- Plan Check / Job No.
- B23WL01219
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2 new single story ADU's.
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2023 | RICHARD GARCIA |
| Corrections Issued | 5/16/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 5/17/2023 | APPLICANT |
| Plan Check Approved | 6/8/2023 | CAROLEAN BASMA |
| Issued | 6/14/2023 | APPLICANT |
| CofO in Progress | 4/27/2024 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 9/21/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
| CofO Issued | 9/25/2024 | RUBEN SALAS |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 5/24/2023 | MAXFIELD VERMY |
| ZI | Cleared | 5/25/2023 | CARTER HOWE |
| ZI | Cleared | 5/25/2023 | JASON CHAN |
| Address approval | Cleared | 6/4/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 6/5/2023 | HUGO LOPEZ |
| Low Impact Development (LID) | Cleared | 6/8/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/8/2023 | HUGO LOPEZ |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Renovation Builders Inc; Lic. No.: 1094029-B | 20831 VALERIO ST WINNETKA, CA 91306 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 7/7/2023 | Corrections Issued | BRENDAN MORELLI |
| Sewer | 7/7/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 7/12/2023 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 7/12/2023 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 7/12/2023 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 7/17/2023 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/17/2023 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 7/17/2023 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/15/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 9/22/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/3/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/12/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/4/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/4/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 1/26/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/26/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/26/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Not Ready | JOSE MACIAS |
| Final | 2/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/16/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 4/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/22/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/26/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gas Test | 4/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Final | 5/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/20/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |