5665-5667 N CASE AVE 91601
Certificate Information: 5665-5667 N CASE AVE 91601
- Application / Permit
- 23010-30000-01843
- Plan Check / Job No.
- B23WL01148
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 3-story duplex w./ att. 2-car carport at front of the lot
- Permit Issued
- Issued on 11/6/2023
- Issuing Office
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | REZA HAGHIGHAT |
| Corrections Issued | 5/11/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 5/18/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 5/19/2023 | APPLICANT |
| Plan Check Approved | 10/17/2023 | REZA HAGHIGHAT |
| Issued | 11/6/2023 | APPLICANT |
| CofO in Progress | 7/29/2025 | JOSE AVILA |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
| CofO Issued | 8/5/2025 | RUBEN SALAS |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2023 | NIKKI ZULUETA |
| SB8 RUD | Cleared | 5/8/2023 | KENNETH LE |
| Sewer availability | Cleared | 5/8/2023 | NIKKI ZULUETA |
| Frnt yard landscape/Water mgmt | Cleared | 5/16/2023 | BRENNEN OBETO |
| Low Impact Development (LID) | Cleared | 5/19/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/23/2023 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 6/14/2023 | LAVEON RIDER |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 15831 SAN JOSE AVE LA PUENTE, CA 91744 |
| Engineer | Desai,, Anil T; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 1/24/2024 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 1/29/2024 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 1/29/2024 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 1/29/2024 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 2/9/2024 | Not Ready for Inspection | KIRK SANDERS |
| Underground Mechanical | 2/9/2024 | Partial Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 2/12/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/12/2024 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 3/1/2024 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 3/5/2024 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 3/12/2024 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 3/12/2024 | Approved | JOHN HAYES |
| Sewer | 3/21/2024 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Approved | JOHN HAYES |
| Special/Order Compliance | 4/4/2024 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 6/25/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Rough | 7/23/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 7/23/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/1/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 8/7/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/7/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 8/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/9/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/9/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/12/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 8/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/23/2024 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 8/23/2024 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 9/4/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 9/4/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 9/4/2024 | Approved | JOSE AVILA |
| Green Building Rough | 9/9/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/10/2024 | Approved | JOSE AVILA |
| Insulation | 9/18/2024 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 9/25/2024 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 9/25/2024 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/25/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 9/25/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Special/Order Compliance | 9/26/2024 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 10/1/2024 | Approved | JOSE AVILA |
| Underground Mechanical | 1/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 5/6/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 5/6/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 5/16/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 5/16/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 5/23/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 5/23/2025 | Conditional Approval | JOSE AVILA |
| PLUMBING-Final | 5/30/2025 | Conditional Approval | JOSE AVILA |
| Green Building Final | 6/11/2025 | Approved | JOSE AVILA |
| HVAC-Final | 6/11/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 6/11/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/11/2025 | SGSOV Not Required | JOSE AVILA |
| Smoke Detectors | 6/11/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 6/24/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 6/24/2025 | Approved | JOSE AVILA |
| Final | 7/15/2025 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 7/15/2025 | Approved | JOSE AVILA |
| Structural Steel Frame | 7/15/2025 | Approved | JOSE AVILA |