1648 S CENTINELA AVE 90025

Certificate Information: 1648 S CENTINELA AVE 90025

Application / Permit
23010-30000-01837
Plan Check / Job No.
B23WL01141
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DET 2 STORY ADU per PER LAMC 12.22 A.33(c) AND (d) AT REAR OF THE LOT WITH 2 CAR GARAGE WITH ATTACHED TRELLIS.
Permit Issued
Issued on 10/13/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 YASHAR EMAMI
Corrections Issued 6/9/2023 YASHAR EMAMI
Quality Review Completed 6/15/2023 CHIHARU SUZUKI
Building Plans Picked Up 6/16/2023 APPLICANT
Applicant returned to address corrections 8/29/2023 YASHAR EMAMI
Applicant returned to address corrections 8/31/2023 YASHAR EMAMI
Applicant returned to address corrections 9/18/2023 YASHAR EMAMI
Plan Check Approved 10/4/2023 YASHAR EMAMI
Issued 10/13/2023 APPLICANT
CofO in Progress 3/27/2025 KIRK SANDERS
Permit Finaled 4/21/2025 RICHARD STEINBACH
CofO Issued 4/21/2025 RICHARD STEINBACH
Permit Finaled 4/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/28/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 6/28/2023 DARIN LAM
Permit Cleared 6/28/2023 DARIN LAM
Sewer availability Cleared 6/28/2023 DARIN LAM
Specific Plan Cleared 7/19/2023 ALESSANDRO MERCURI
Construction near power lines Cleared 7/20/2023 NADER ISKANDER
Trees in Parkway Cleared 8/15/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 9/28/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 9/28/2023 DARIN LAM

Contact Information

Architect Urmston,, David Paul; Lic. No.: C10564 2130 SO. SAWTELLE BLVD 314      LOS ANGELES, CA 90025
Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/28/2023 Not Ready for Inspection BEN MOLSTAD
Underground Mechanical 1/9/2024 Approved BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 1/17/2024 Approved BEN MOLSTAD
Sewer 1/19/2024 Partial Approval BEN MOLSTAD
Deputy Reinf. Concrete 1/22/2024 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 1/26/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 2/15/2024 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Corrections Issued ASHLEY THOMPSON
Green Building Rough 2/15/2024 Not Ready for Inspection ASHLEY THOMPSON
Verify Sprinkler Sign Off 2/15/2024 Not Ready for Inspection ASHLEY THOMPSON
Wood Frame 2/15/2024 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval ASHLEY THOMPSON
HVAC-Rough 4/17/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 4/17/2024 Partial Approval MEL KHACHATOURIAN
Rough-Elec/Plmb/HVAC 4/25/2024 Corrections Issued ASHLEY THOMPSON
Sewer 4/25/2024 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 5/3/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 5/3/2024 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Approved ASHLEY THOMPSON
Green Building Rough 5/3/2024 Approved ASHLEY THOMPSON
HVAC-Rough 5/3/2024 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 5/3/2024 Partial Approval ASHLEY THOMPSON
PLUMBING-Rough 5/3/2024 Approved ASHLEY THOMPSON
Wood Frame 5/3/2024 Approved ASHLEY THOMPSON
Insulation 5/13/2024 Approved ASHLEY THOMPSON
Sewer 5/13/2024 Approved ASHLEY THOMPSON
Shower Pan 5/13/2024 Corrections Issued ASHLEY THOMPSON
Special/Order Compliance 5/13/2024 Partial Inspection KIRK SANDERS
Drywall Nailing 5/28/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 5/28/2024 Approved KIRK SANDERS
Shower Pan 5/28/2024 Approved KIRK SANDERS
ELECTRICAL-Final 8/29/2024 Corrections Issued KIRK SANDERS
Special/Order Compliance 8/29/2024 Corrections Issued KIRK SANDERS
Underground Mechanical 8/29/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Final 9/16/2024 Corrections Issued KIRK SANDERS
HVAC-Final 10/4/2024 Approved KIRK SANDERS
PLUMBING-Final 10/4/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 12/31/2024 Not Ready for Inspection KIRK SANDERS
Final 12/31/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 12/31/2024 Approved KIRK SANDERS
Green Building Final 12/31/2024 Approved KIRK SANDERS
PLUMBING-Final 12/31/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 12/31/2024 SGSOV Not Ready KIRK SANDERS
Service/Power Release 12/31/2024 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 12/31/2024 Approved KIRK SANDERS
ELECTRICAL-Final 2/21/2025 Approved KIRK SANDERS
Final 2/21/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Not Ready KIRK SANDERS
Final 3/26/2025 OK to Issue CofO KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/26/2025 SGSOV Approved KIRK SANDERS
Service/Power Release 3/26/2025 Approved KIRK SANDERS
Special/Order Compliance 3/26/2025 Approved KIRK SANDERS