13020 W EUSTACE ST 91331
Certificate Information: 13020 W EUSTACE ST 91331
- Application / Permit
- 23010-30000-01756
- Plan Check / Job No.
- B23WL01062
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- New Detached 2-Car Carport PER LADBS STANDARD PLAN
- Permit Issued
- Issued on 3/6/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | YASHAR EMAMI |
| Corrections Issued | 6/8/2023 | YASHAR EMAMI |
| Quality Review Completed | 6/12/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/13/2023 | APPLICANT |
| Applicant returned to address corrections | 7/28/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/16/2023 | YASHAR EMAMI |
| Plan Check Approved | 2/23/2024 | YASHAR EMAMI |
| Issued | 3/6/2024 | APPLICANT |
| CofO in Progress | 6/13/2025 | MICHEL ABAJAN |
| Permit Finaled | 7/1/2025 | RUBEN SALAS |
| CofO Issued | 7/1/2025 | RUBEN SALAS |
| Permit Finaled | 7/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 1/5/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/25/2024 | COLIN LOREDO |
| Clean Up Green Up | Cleared | 2/1/2024 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/5/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/9/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 5/9/2024 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 8/1/2024 | Approved | MICHEL ABAJAN |
| Final | 6/12/2025 | OK to Issue CofO | MICHEL ABAJAN |
| MERV13>=Final | 6/12/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 6/12/2025 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 6/12/2025 | Approved | MICHEL ABAJAN |