17449 W BURMA ST 91316

Certificate Information: 17449 W BURMA ST 91316

Application / Permit
23010-30000-01749
Plan Check / Job No.
B23WL01058
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story ADU at rear of the lot per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 4/30/2024
Issuing Office
West Los Angeles
Current Status
CofO in Progress on 5/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/24/2023 APPLICANT
Assigned to Plan Check Engineer 5/3/2023 REZA HAGHIGHAT
Corrections Issued 5/7/2023 REZA HAGHIGHAT
Quality Review Completed 5/11/2023 KAVIAN REFAHI
Building Plans Picked Up 5/16/2023 APPLICANT
Plan Check Approved 3/5/2024 REZA HAGHIGHAT
Issued 4/30/2024 APPLICANT
CofO in Progress 5/7/2026 MORRIS JACKSON

Permit Application Clearance Information

Address approval Cleared 6/7/2023 FERNANDO GIL
ZI Cleared 6/13/2023 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 6/14/2023 FERNANDO GIL
Sewer availability Cleared 6/14/2023 FERNANDO GIL
Hydrant and Access approval Cleared 6/30/2023 GILBERT URREA
Low Impact Development (LID) Cleared 1/6/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 1/11/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Mangoli,, Arash; Lic. No.: C84319 1727 BENTLEY AVE APT 211      LOS ANGELES, CA 90025

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/19/2025 Partial Approval MORRIS JACKSON
Footing/Foundation/Slab 9/25/2025 Approved MORRIS JACKSON
Sewer 9/25/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Partial Approval MORRIS JACKSON
Deputy Wood Construction 10/14/2025 Conditional Approval MORRIS JACKSON
Deputy Wood Construction 10/22/2025 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 10/28/2025 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 No Access for Inspection MORRIS JACKSON
HVAC-Rough 10/28/2025 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 10/28/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 11/5/2025 Partial Approval MORRIS JACKSON
HVAC-Rough 11/5/2025 Approved MORRIS JACKSON
Special/Order Compliance 11/5/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 11/13/2025 Partial Approval MORRIS JACKSON
Green Building Rough 11/13/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/13/2025 Partial Approval MORRIS JACKSON
Shower Pan 11/13/2025 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 11/13/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 11/17/2025 Approved MORRIS JACKSON
Insulation 11/17/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/17/2025 Approved MORRIS JACKSON
Drywall Nailing 11/20/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 2/12/2026 Approved MORRIS JACKSON
HVAC-Final 2/12/2026 Approved MORRIS JACKSON
PLUMBING-Final 2/12/2026 Approved MORRIS JACKSON
Service/Power Release 2/12/2026 Not Ready for Inspection MORRIS JACKSON
Final 3/13/2026 Corrections Issued MORRIS JACKSON
Green Building Final 3/13/2026 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Approved MORRIS JACKSON
Service/Power Release 3/13/2026 Partial Inspection MORRIS JACKSON
Smoke Detectors 3/13/2026 Approved MORRIS JACKSON
Final 4/29/2026 No Access for Inspection MORRIS JACKSON
Service/Power Release 4/29/2026 No Access for Inspection MORRIS JACKSON
Final 5/4/2026 Partial Approval MORRIS JACKSON
Service/Power Release 5/4/2026 Approved MORRIS JACKSON
Final 5/6/2026 Corrections Issued MORRIS JACKSON
Final 5/7/2026 OK to Issue CofO MORRIS JACKSON