Excavation/Setback/Form/Re-Bar
|
5/23/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/24/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
Reinforced Concrete Frame
|
6/5/2024
|
Partial Approval
|
JESUS RODRIGUEZ
|
|
Sewer
|
6/10/2024
|
Approved
|
KIRK SANDERS
|
|
Underground Mechanical
|
6/10/2024
|
Partial Approval
|
KIRK SANDERS
|
|
Excavation/Setback/Form/Re-Bar
|
6/18/2024
|
Partial Approval
|
ASHLEY THOMPSON
|
|
Footing/Foundation/Slab
|
6/18/2024
|
Partial Approval
|
ASHLEY THOMPSON
|
|
METHANE-Barrier
|
6/18/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
METHANE-Subgrade
|
6/18/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Footing/Foundation/Slab
|
6/24/2024
|
Partial Approval
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
7/11/2024
|
Partial Approval
|
ASHLEY THOMPSON
|
|
Reinforced Concrete Frame
|
7/16/2024
|
Partial Approval
|
ARAM AVEDISIAN
|
|
Excavation/Setback/Form/Re-Bar
|
7/23/2024
|
Partial Approval
|
ASHLEY THOMPSON
|
|
Reinforced Concrete Frame
|
7/26/2024
|
Partial Approval
|
ASHLEY THOMPSON
|
|
Excavation/Setback/Form/Re-Bar
|
8/1/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Footing/Foundation/Slab
|
8/7/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
METHANE-Barrier
|
8/7/2024
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
METHANE-Subgrade
|
8/7/2024
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
Reinforced Concrete Frame
|
8/7/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Special/Order Compliance
|
8/7/2024
|
Partial Inspection
|
REGINA MENDEZ
|
|
Deputy Reinf. Concrete
|
8/8/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Footing/Foundation/Slab
|
9/3/2024
|
Partial Approval
|
ASHLEY THOMPSON
|
|
METHANE-Barrier
|
9/3/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
METHANE-Rough
|
9/3/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
METHANE-Subgrade
|
9/3/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Structural Steel Frame
|
9/3/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Footing/Foundation/Slab
|
9/6/2024
|
Corrections Issued
|
KIRK SANDERS
|
|
METHANE-Barrier
|
9/6/2024
|
Corrections Issued
|
KIRK SANDERS
|
|
METHANE-Subgrade
|
9/6/2024
|
Approved
|
KIRK SANDERS
|
|
Footing/Foundation/Slab
|
9/23/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
METHANE-Barrier
|
9/23/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
METHANE-Final
|
9/23/2024
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
PLUMBING-Rough
|
9/23/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
PLUMBING-Rough
|
9/25/2024
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/26/2024
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Footing/Foundation/Slab
|
9/26/2024
|
Approved
|
STEPHANIE SWANSON
|
|
METHANE-Barrier
|
9/26/2024
|
Approved
|
STEPHANIE SWANSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/11/2024
|
Corrections Issued
|
REGINA MENDEZ
|
|
Deputy Wood Construction
|
10/15/2024
|
Conditional Approval
|
ASHLEY THOMPSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/16/2024
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/18/2024
|
Partial Approval
|
ASHLEY THOMPSON
|
|
Deputy Wood Construction
|
11/4/2024
|
Conditional Approval
|
ASHLEY THOMPSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/4/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
Deputy Wood Construction
|
12/3/2024
|
Approved
|
ASHLEY THOMPSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/3/2024
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
Final
|
12/12/2024
|
Corrections Issued
|
KIRK SANDERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/12/2024
|
Conditional Approval
|
KIRK SANDERS
|
|
Deputy Drilled-In Anchors
|
2/3/2025
|
Conditional Approval
|
ASHLEY THOMPSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/5/2025
|
Partial Approval
|
BOBBY KEY
|
|
ELECTRICAL-Rough
|
2/26/2025
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
HVAC-Rough
|
2/26/2025
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
PLUMBING-Rough
|
2/26/2025
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Rough
|
3/7/2025
|
Corrections Issued
|
BOBBY KEY
|
|
HVAC-Rough
|
3/7/2025
|
Corrections Issued
|
BOBBY KEY
|
|
Interior/Exterior Lathing
|
3/7/2025
|
Corrections Issued
|
BOBBY KEY
|
|
PLUMBING-Rough
|
3/7/2025
|
Not Ready for Inspection
|
BOBBY KEY
|
|
Special/Order Compliance
|
3/7/2025
|
Partial Inspection
|
WILBER ROSALES
|
|
ELECTRICAL-Rough
|
3/13/2025
|
Approved
|
ARAM AVEDISIAN
|
|
HVAC-Rough
|
3/13/2025
|
Approved
|
ARAM AVEDISIAN
|
|
PLUMBING-Rough
|
3/13/2025
|
Not Ready for Inspection
|
ARAM AVEDISIAN
|
|
Interior/Exterior Lathing
|
3/17/2025
|
Partial Approval
|
ASHLEY THOMPSON
|
|
PLUMBING-Rough
|
3/17/2025
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
BUILDING-Rough-Frame
|
3/19/2025
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Green Building Rough
|
3/19/2025
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
METHANE-Rough
|
3/19/2025
|
Approved
|
ASHLEY THOMPSON
|
|
Verify Sprinkler Sign Off
|
3/19/2025
|
Approved
|
ASHLEY THOMPSON
|
|
Insulation
|
3/21/2025
|
Partial Approval
|
JAYLIN GRAVITTE
|
|
BUILDING-Rough-Frame
|
3/25/2025
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Special/Order Compliance
|
3/25/2025
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
BUILDING-Rough-Frame
|
3/27/2025
|
Approved
|
ARAM AVEDISIAN
|
|
Green Building Rough
|
3/27/2025
|
Approved
|
ARAM AVEDISIAN
|
|
Insulation
|
4/2/2025
|
Approved
|
JAYLIN GRAVITTE
|
|
Drywall Nailing
|
4/30/2025
|
Approved
|
ASHLEY THOMPSON
|
|
Interior/Exterior Lathing
|
5/19/2025
|
Approved
|
ASHLEY THOMPSON
|
|
Shower Pan
|
5/19/2025
|
Approved
|
ASHLEY THOMPSON
|
|
Special/Order Compliance
|
5/19/2025
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
Pre-Inspection
|
10/14/2025
|
Partial Inspection
|
ASHLEY THOMPSON
|
|
Sewer
|
11/4/2025
|
Partial Inspection
|
JESUS PINEDA
|
|
ELECTRICAL-Final
|
3/18/2026
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
ELECTRICAL-Final
|
4/2/2026
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
ELECTRICAL-Final
|
5/14/2026
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
PLUMBING-Final
|
5/14/2026
|
Approved
|
ASHLEY THOMPSON
|
|
HVAC-Final
|
5/20/2026
|
Corrections Issued
|
RYAN SALAZAR
|
|
Final
|
6/29/2026
|
Corrections Issued
|
ASHLEY THOMPSON
|
|
Green Building Final
|
6/29/2026
|
Approved
|
ASHLEY THOMPSON
|
|
SGSOV-Seismic Gas S/O Valve
|
6/29/2026
|
SGSOV Not Required
|
ASHLEY THOMPSON
|
|
Service/Power Release
|
6/29/2026
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Smoke Detectors
|
6/29/2026
|
Approved
|
ASHLEY THOMPSON
|
|
Final
|
7/16/2026
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|
|
Service/Power Release
|
7/16/2026
|
Not Ready for Inspection
|
ASHLEY THOMPSON
|