122 S GLENROY AVE 90049
Certificate Information: 122 S GLENROY AVE 90049
- Application / Permit
- 23010-30000-01353
- Plan Check / Job No.
- B23WL00843
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached 1-story ADU (445 sf) with attached trellised roof patio cover (21' x 13') at rear of the lot per GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 10/18/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | REZA HAGHIGHAT |
| Corrections Issued | 4/13/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 4/25/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 4/27/2023 | APPLICANT |
| Applicant returned to address corrections | 6/5/2023 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 8/2/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 10/18/2023 | REZA HAGHIGHAT |
| Issued | 10/18/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2023 | DARIN LAM |
| Permit | Cleared | 6/29/2023 | DARIN LAM |
| Sewer availability | Cleared | 6/29/2023 | DARIN LAM |
| Hydrant and Access approval | Cleared | 8/4/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 9/18/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/18/2023 | DARIN LAM |
| Excavation more than 5-ft deep | Cleared | 10/4/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 10/4/2023 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 10/4/2023 | REZA HAGHIGHAT |
| Trees in Parkway | Cleared | 10/17/2023 | ADALBERTO VERA |
Contact Information
| Architect | , ; Lic. No.: C35626 | 607 VIA LOS MIRADORES REDONDO BEACH, CA 90277 |
| Contractor | C & C Partners Design/Build Firm Inc; Lic. No.: 654337-B | 508 N PACIFIC COAST HWY REDONDO BEACH, CA 90277 |
| Engineer | Garcia,, Lionel J; Lic. No.: C58475 | 24702 NARBONNE AVE LOMITA, CA 90717 |
| Engineer | Soto,, Miguel Angel; Lic. No.: C87493 | 653 W 5TH ST SAN PEDRO, CA 90731 |
| Geologist | , ; Lic. No.: GEO841 | PO BOX 8133 HUNTINGTON BEACH, CA 92615 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/29/2024 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/1/2024 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 8/28/2024 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/17/2024 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/20/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/14/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/27/2024 | Approved | CARLOS MATAMOROS |
| Shower Pan | 12/2/2024 | Approved | REGINA MENDEZ |
| ELECTRICAL-Rough | 12/20/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/23/2024 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 2/24/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 3/11/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 3/11/2025 | Approved | CARLOS MATAMOROS |
| Insulation | 3/14/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 3/21/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/24/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/7/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 11/7/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 12/8/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 12/8/2025 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 3/2/2026 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 3/2/2026 | Approved | EVAN COOPER |
| Final | 3/2/2026 | Partial Inspection | EVAN COOPER |
| Green Building Final | 3/2/2026 | Approved | EVAN COOPER |
| HVAC-Final | 3/2/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/2/2026 | Approved | EVAN COOPER |
| Reinforced Concrete Frame | 3/2/2026 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 3/2/2026 | Approved | EVAN COOPER |
| Smoke Detectors | 3/2/2026 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/2/2026 | Approved | EVAN COOPER |