300 S CARMELINA AVE 90049
Certificate Information: 300 S CARMELINA AVE 90049
- Application / Permit
- 23010-30000-01260
- Plan Check / Job No.
- B23WL00797
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD w./ att. 2-car garage and 1-level basement
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 6/29/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2023 | REZA HAGHIGHAT |
| Corrections Issued | 4/5/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 4/11/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 4/12/2023 | APPLICANT |
| Applicant returned to address corrections | 6/7/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 6/29/2023 | REZA HAGHIGHAT |
| Issued | 6/29/2023 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/17/2023 | KURT CORRAL |
| Work Adjacent to Public Way | Cleared | 4/21/2023 | KATHLEEN LEE |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | KATHLEEN LEE |
| Permit | Cleared | 4/27/2023 | KATHLEEN LEE |
| Sewer availability | Cleared | 4/28/2023 | KATHLEEN LEE |
| Low Impact Development (LID) | Cleared | 6/1/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 6/2/2023 | KATHLEEN LEE |
| Trees in Parkway | Cleared | 6/6/2023 | ADALBERTO VERA |
| Excavation more than 5-ft deep | Cleared | 6/7/2023 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 6/7/2023 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 6/7/2023 | REZA HAGHIGHAT |
Contact Information
| Architect | Blumenberg,, Richard Leo; Lic. No.: C10862 | 15200 SUNSET BLVD STE 201 PACIFIC PALISADES, CA 90272 |
| Contractor | Owner-Builder | , |
| Engineer | Bains,, Gagan Prit Singh; Lic. No.: S4482 | 222 E HUNTINGTON DR STE 235 MONROVIA, CA 91016 |
| Geologist | , ; Lic. No.: GEO2781 | 11823 SLAUSON AVE STE 46 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/20/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 9/20/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Shotcrete | 10/23/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/26/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 10/30/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 12/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 12/15/2023 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Steel/Welding | 1/26/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 2/9/2024 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/14/2024 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 7/25/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 7/25/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 12/23/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 12/29/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 12/29/2025 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/24/2026 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Approved | HERBERT GIRON |
| Green Building Rough | 2/24/2026 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/24/2026 | Partial Approval | HERBERT GIRON |
| Verify Sprinkler Sign Off | 2/24/2026 | Approved | HERBERT GIRON |
| Insulation | 3/13/2026 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/2/2026 | Approved | HERBERT GIRON |
| Drywall Nailing | 4/2/2026 | Approved | HERBERT GIRON |
| Shower Pan | 5/14/2026 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 6/24/2026 | Not Ready for Inspection | KEVIN SARGSYAN |