10432 N DENSMORE AVE 91344
Certificate Information: 10432 N DENSMORE AVE 91344
- Application / Permit
- 23010-30000-01151
- Plan Check / Job No.
- B23VN02947
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan. N 2-story SFD per SB9, 2 unit development. ** 2 of 3 **
- Permit Issued
- Issued on 7/28/2023
- Issuing Office
- Current Status
- CofO Issued on 5/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | KAVIAN REFAHI |
| Corrections Issued | 3/22/2023 | KAVIAN REFAHI |
| Quality Review Completed | 3/28/2023 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 6/13/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 6/22/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/24/2023 | KAVIAN REFAHI |
| Plan Check Approved | 7/25/2023 | KAVIAN REFAHI |
| Issued | 7/28/2023 | APPLICANT |
| CofO in Progress | 5/1/2024 | PIERRE VEGA |
| Permit Finaled | 5/17/2024 | DAVID JAMES |
| CofO Issued | 5/17/2024 | DAVID JAMES |
| Permit Finaled | 5/17/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 4/1/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/3/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 4/15/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 4/28/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 5/1/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 7/24/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/1/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 8/1/2023 | Corrections Issued | MARIO CUEVAS |
| PLUMBING-Rough | 8/7/2023 | Not Ready for Inspection | MARIO CUEVAS |
| Underground Mechanical | 8/7/2023 | Approved | MARIO CUEVAS |
| Footing/Foundation/Slab | 8/10/2023 | Corrections Issued | MARIO CUEVAS |
| Footing/Foundation/Slab | 8/15/2023 | Approved | MARIO CUEVAS |
| BUILDING-Rough-Frame | 8/29/2023 | Not Ready for Inspection | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Approved | PIERRE VEGA |
| Green Building Rough | 8/29/2023 | Not Ready for Inspection | PIERRE VEGA |
| Verify Sprinkler Sign Off | 8/29/2023 | Not Ready for Inspection | PIERRE VEGA |
| Deputy Wood Construction | 9/15/2023 | No Access for Inspection | DAVID JAMES |
| BUILDING-Rough-Frame | 9/27/2023 | Corrections Issued | GARY PARKER |
| ELECTRICAL-Rough | 9/27/2023 | Corrections Issued | GARY PARKER |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Corrections Issued | GARY PARKER |
| Green Building Rough | 9/27/2023 | Corrections Issued | GARY PARKER |
| HVAC-Rough | 9/27/2023 | Corrections Issued | GARY PARKER |
| PLUMBING-Rough | 9/27/2023 | Corrections Issued | GARY PARKER |
| Verify Sprinkler Sign Off | 9/27/2023 | Corrections Issued | GARY PARKER |
| ELECTRICAL-Rough | 10/3/2023 | Corrections Issued | GARY PARKER |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Corrections Issued | GARY PARKER |
| HVAC-Rough | 10/3/2023 | Corrections Issued | GARY PARKER |
| PLUMBING-Rough | 10/3/2023 | Corrections Issued | GARY PARKER |
| Special/Order Compliance | 10/3/2023 | Corrections Issued | GARY PARKER |
| Sewer | 10/18/2023 | Approved | GARY PARKER |
| ELECTRICAL-Rough | 11/3/2023 | No Access for Inspection | MARK DOVICO |
| HVAC-Rough | 11/3/2023 | No Access for Inspection | MARK DOVICO |
| PLUMBING-Rough | 11/3/2023 | No Access for Inspection | MARK DOVICO |
| Rough-Elec/Plmb/HVAC | 11/3/2023 | No Access for Inspection | MARK DOVICO |
| Sewer | 11/3/2023 | No Access for Inspection | MARK DOVICO |
| BUILDING-Rough-Frame | 11/7/2023 | Partial Approval | PIERRE VEGA |
| ELECTRICAL-Rough | 11/7/2023 | Approved | PIERRE VEGA |
| HVAC-Rough | 11/7/2023 | Approved | PIERRE VEGA |
| PLUMBING-Rough | 11/7/2023 | Not Ready for Inspection | PIERRE VEGA |
| Sewer | 11/7/2023 | Approved | PIERRE VEGA |
| ELECTRICAL-Rough | 11/8/2023 | Approved | PIERRE VEGA |
| HVAC-Rough | 11/8/2023 | Approved | PIERRE VEGA |
| PLUMBING-Rough | 11/8/2023 | Not Ready for Inspection | PIERRE VEGA |
| Sewer | 11/8/2023 | Approved | PIERRE VEGA |
| Interior/Exterior Lathing | 11/17/2023 | Not Ready for Inspection | MARK DOVICO |
| Interior/Exterior Lathing | 12/5/2023 | Approved | PIERRE VEGA |
| Insulation | 12/8/2023 | Approved | PIERRE VEGA |
| Drywall Nailing | 12/18/2023 | Corrections Issued | GARY PARKER |
| Underground Mechanical | 12/18/2023 | Corrections Issued | GARY PARKER |
| Drywall Nailing | 12/20/2023 | Approved | GARY PARKER |
| PLUMBING-Rough | 12/20/2023 | Corrections Issued | GARY PARKER |
| Underground Mechanical | 12/28/2023 | Corrections Issued | GARY PARKER |
| Underground Mechanical | 1/2/2024 | Approved | GARY PARKER |
| BUILDING-Rough-Frame | 3/18/2024 | Approved | MARK DOVICO |
| Final | 3/18/2024 | OK to Issue CofO | MARK DOVICO |
| Green Building Final | 3/18/2024 | Approved | MARK DOVICO |
| Green Building Rough | 3/18/2024 | Approved | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 3/18/2024 | SGSOV Approved | MARK DOVICO |
| Service/Power Release | 3/18/2024 | Approved | MARK DOVICO |
| Smoke Detectors | 3/18/2024 | Approved | MARK DOVICO |
| Verify Sprinkler Sign Off | 3/18/2024 | Approved | MARK DOVICO |