9615 W CRESTA DR 90035
Certificate Information: 9615 W CRESTA DR 90035
- Application / Permit
- 23010-30000-01031
- Plan Check / Job No.
- B23WL00629
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2- sotory SFD w/ att garage *** 1 of 2 **
- Permit Issued
- Issued on 12/13/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | KAVIAN REFAHI |
| Corrections Issued | 3/18/2023 | KAVIAN REFAHI |
| Quality Review Completed | 3/20/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/21/2023 | APPLICANT |
| Applicant returned to address corrections | 7/26/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/9/2023 | KAVIAN REFAHI |
| Plan Check Approved | 12/6/2023 | KAVIAN REFAHI |
| Issued | 12/13/2023 | APPLICANT |
| CofO in Progress | 3/6/2025 | ARAM AVEDISIAN |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
| CofO Issued | 3/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2023 | DARIN LAM |
| Miscellaneous | Cleared | 8/14/2023 | JAZMIN ROQUE |
| Permit | Cleared | 8/14/2023 | DARIN LAM |
| Sewer availability | Cleared | 8/14/2023 | DARIN LAM |
| ZA Case | Cleared | 8/14/2023 | JAZMIN ROQUE |
| Trees in Parkway | Cleared | 8/28/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 9/30/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 10/5/2023 | TRISH PARAS |
| Roof/Waste drainage to street | Cleared | 10/5/2023 | DARIN LAM |
| GPI Written Notices | Cleared | 12/6/2023 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 12/6/2023 | KAVIAN REFAHI |
Contact Information
| Architect | Cunningham,, Patrick Joseph; Lic. No.: C35626 | 607 VIA LOS MIRADORES REDONDO BEACH, CA 90277 |
| Contractor | C & C Partners Design/Build Firm Inc; Lic. No.: 654337-B | 508 N PACIFIC COAST HWY REDONDO BEACH, CA 90277 |
| Engineer | Garcia,, Lionel J; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/18/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Rough | 1/29/2024 | Off-Hour Fees Due | |
| METHANE-Rough | 1/30/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 1/31/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 2/8/2024 | Approved | OGANES TARAKHCHYAN |
| METHANE-Final | 2/8/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/18/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 4/18/2024 | Approved | OGANES TARAKHCHYAN |
| Sewer | 5/1/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/10/2024 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 5/10/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/22/2024 | Conditional Approval | MEL KHACHATOURIAN |
| Green Building Rough | 5/22/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 5/22/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/22/2024 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 6/7/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 6/7/2024 | Approved | SEAN HAUPT |
| HVAC-Rough | 6/7/2024 | Approved | SEAN HAUPT |
| Insulation | 6/24/2024 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 7/2/2024 | Approved | ASHLEY THOMPSON |
| Insulation | 7/2/2024 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/2/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 11/1/2024 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 11/1/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 11/4/2024 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 11/12/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 11/12/2024 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 11/12/2024 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 11/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 12/11/2024 | Approved | ASHLEY THOMPSON |
| Final | 12/23/2024 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 12/23/2024 | Approved | ARAM AVEDISIAN |
| Green Building Final | 12/23/2024 | Approved | ARAM AVEDISIAN |
| METHANE-Barrier | 12/23/2024 | Approved | ARAM AVEDISIAN |
| METHANE-Subgrade | 12/23/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 12/23/2024 | Approved | ARAM AVEDISIAN |
| Final | 3/6/2025 | OK to Issue CofO | ARAM AVEDISIAN |